A contractor undertook to finish work in 92 days and employed 110 men. After 48 days he found that he had already done 3/5 work the number of men he can withdraw so that his work may still be finished in time is : a 45 b 40 c 35 d 30
Correct option d 30Explanation: ‘n’ no of men can withdrawn
Related Solutions
A contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done part of the work, the number of men he can withdraw so that the work may still be finished in time is :
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done of the work. How many men can be discharge now so that the work may finish in time?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done of the work.
How many men can be discharged now so that the work may finish in time?
View SolutionA contractor took a contract to finish a work in 80 days. He employed 300 men and after 60 days he had to employ 100 more men and then the work was finished 2 days earlier. By how many days would the work be finished if 100 extra men were not employed?
View SolutionA contractor took a contract to complete a work in 40 days. He initially employed 100 men and after 35 days, he employed 100 more and completed the work on time. If that extra person had not employed then after how many days would the work have been finished after the right time?
View SolutionA contractor takes a contract to get a work done in 38 days. Employing 30 men, he works for 25 days. Later, by employing 5 more people, he gets the work completed in one day, if 5 more people had not come, then by how many days would the work be finished late?
View Solutionएक ठेकेदार 92 दिनों में किसी को पूरा करने का टेका लेता है और वह इसके लिए 110 लोगो को काम पर लगता है 48 दिनों के बाद वह पता है कि उसने भाग काम का ख़त्म कर दिया है , तो काम समय पर ख़त्म हो ख़त्म हो इसके लिए वह कितने लोगो को काम पर से हटा सकता है
View Solution15 men can finish a piece of work in 40 days. The number of days after which 5 men should leave the work so that the work is finished in 45 days altogether is:
View SolutionIf 45 men can finish a piece of work in 12 days, in how many days will 30 men finish the same work?
View Solution120 men working 10 hours a day can finish a piece of work in 85 days. After 10 days all the men went on strike and the work was stopped for 25 days. In order to finish the work on time, additional men should be employed so that they can finish the work on time by working 8 hours a day?
View SolutionA contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that of the work was still to be done. How many more men were required to complete the work in stipulated time?
View Solution45 आदमी किसी कार्य को 49 दिन में समाप्त करते हैं, तो 35 आदमी उसी कार्य को कितने दिन में समाप्त करेंगे?
View SolutionA contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men. Then after how many days from scheduled time the wrok would be finished?
View Solution36 workmen are employed to finish a certain work in 48 days. But it is found that in 24 days only 2/5 work is done. How many more men must be employed to finish the work in time?
View SolutionA contractor undertook to complete the work in 40 days and he deployed 20 men for his work. 8 days before the scheduled time he realised that th of the work was still to be done. How many more men were required.to complete the work in stipulated time?
View SolutionA contractor employs 36 men on a job and they do 1/2 of the work in 16 days. He employs 12 additional men to complete the remainder of the work. In how many days will the remaining work be finished?
View Solutionएक ठेकेदार ने किसी काम को 40 दिन में खत्म करने के लिये 100 आदमी को काम पर लगा दिया, 35 दिन बाद 100 और आदमियों को काम पर लगाया तो काम खत्म हुआ। अगर ये 100 और आदमी नहीं लगाये होते तो काम कितने दिन में खत्म होता?
View Solution