Some persons can do a piece of work in 12 days. Two times the number of such persons will do half of the work in: a 9 days b 6 days c 5 days d 3 days
Correct option d 3 daysExplanation:Let there are N persons in the beginning and Let there was 2 units of work in beginning.
Related Solutions
Some persons can do piece of work in 12 days. Two times the number of such persons will do half of the work in
(A) 9 days (B) 6 days (C) 5 days (D) 3 days
View SolutionSome persons can do a piece of work in 12 days. Two times the number of such persons will do half of the work in
View Solution36 persons working 8 hours a day can do 3 units of work in 12 days. How many persons are required to do 5 units of that work in 16 days, if they work for 6 hours a day?
प्रतिदिन 8 घंटे कार्य करके 36 लोग किसी कार्य की 3 इकाई 12 दिनों में कर सकते हैं| यदि वे एक दिन में 6 घंटे कार्य करें तो 16 दिन में इस कार्य की 5 इकाई समाप्त करने के लिए कितने लोगों की आवश्यकता होगी ?
View SolutionA and B can do a given piece of work in 8 days, B and C can do the same work in 12 days and A, B, C complete it in 6 days. Number of days required to finish the work by A and C is
View SolutionA can do a piece of work in 6 days, B can do it in 9 days. With the assistance of C they completed the work in 3 days. In how many days can C alone do the work?
View Solution(A + B) can do a piece of work in 12 days. (B + C) can do same work in days. A work for 3 days, B works for 4 days and C completed the remaining work in 7 days. In how many days will A, B and C do this work alone ?
View SolutionA and B can do a piece of work in 12 days. While B and C can do that work in 8 days and C and A can do that work in 6 days then in how much time will B do it?
View SolutionA can do a piece of work in 6 days, B can do the same work in 8 days and C can do the same work in 12 days. In how many days will they do this work together?
View SolutionA can do a piece of work in 20 days which B can do in 12 days. B worked at it for 9 days. A can finish the remaining work in
View SolutionA can do a piece of work in 9 days and B can do the same in 12 days. In how days can the work be completed if A and B work together?
View SolutionIf six men can do a piece of work in 6 days, then 3 men can do same work in
(a) 10 days
(b) 12 days
(c) 15 days
(d) 18 days
View SolutionIf six men can do a piece of work in 6 days, then 3 men can do same work in 10 days (b) 12 days (c) 15 days (d) 18 days
View SolutionIf 3 persons can do a piece of work in 4 days, then 4 persons can do it in …… days.
View SolutionIf 20 persons can do a piece of work in 7 days then calculate the number of persons required to complete the work in 28 days
View SolutionIf 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:
View SolutionIf 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.
View SolutionA and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A, B and C together can do it in 6 days. In how many days will A and C together complete it?
View SolutionIf 5 men can do a piece of work in 28 days then the number of persons required to the same work in 7 days is :
View SolutionSome persons can finish a work in 12 days. In how many days will twice the number of people do the work done by it?
View Solution