7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days?a 28b 21c 14d 7
Correct option c 14 Explanation:n is additional no of men required21 = 7 + nn = 14 men
Related Solutions
7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work
View Solution7 पुरुष 12 दिनों में काम का एक भाग पूरा कर सकते है। 8 दिनों में दोगुना काम को पूरा करने के लिए कितने अतिरिक्त पुरुषो की आवश्यकता होगी ?
View Solution7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?
View Solution7 men can complete a plece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?
View Solution7 men can complete a work in 12 days. How many additional men will be required to complete twice the work in 8 days?
View Solution7 men can complete a work in 12 days. How many additional men are required to complete two times the work in 8 days ?
View Solution15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
View Solution8 men working for 9 hours a day can complete a piece of work in 20 days. In how many days can 7 men working for 10 hours a day complete the same piece of work?
View Solution12 men can do a piece of work in 16 days, then in how many days will 8 men complete the same work?
View Solution21 men can complete a piece of work in days. In how many days can 18 men complete the same piece of work?
View Solution5 men take 20 days to complete a piece of work, they work 8 hours a day. If 8 men work 7 hours a day, in how many days can they complete the work?
View Solution24 men can complete a piece of work in 16 days and 18 women can complete the same work in 32 days. 12 men and 6 women work together for 16 days. If the remaining work was to be completed in 2 days, how many additional men would be required besisdes 12 men and 6 women ?
View Solution16 पुरुष एक काम 7 दिन में पूरा कर सकते है । इसी काम को 28 पुरुष कितने दिन में पूरा करेंगे ?
View SolutionIf 8 men can complete a work in 14 days, then in how much time (in days) will 7 men complete the same work?
View Solution5 men can do a piece of work in 10 days. How many men will be required to complete the work in 5 days?
View Solution45 men can complete a piece of work in 12 days. In how many days will 36 men be able to complete it?
View Solutionयदि 40 पुरुष प्रतिदिन 12 घंटे कार्य करते हुए किसी कार्य को 8 दिनों में पूर्ण कर सकते हैं, तो कितने पुरुष प्रतिदिन 4 घंटे कार्य करते हुए - उसी कार्य को 16 दिनों में पूर्ण कर सकते हैं?
View Solution12 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?
View SolutionIf 10 men can complete a work in 12 days . In how many days can 18 men complete the same work ?
View Solution12 men can do a piece of work in 24 days. How many days are needed to complete the work, if 8 men are engaged in the same work ?
View Solution