A road of 5 km length will be constructed in 100 days. So 280 workers were employed. But after 80 days it was found that only 7/2 km road was completed. Now how many more people were need to finish the work in the specified time? a 480 b 80 c 200 d 100
Correct option c 200 Explanation:Let ‘n’ more number of man are required to complete the job in 20 days.
Related Solutions
A road of 5 km length will be con structed in 100 days. So 280 workers were employed. But after 80 days it was found that only km road was completed. Now how many more people were needed to finish the work in the specified time?
View Solution5 कि मी लम्बी सड़क को 100 दिनों में बनाने के लिए 280 मजरुरो को काम पर लगाया गया । लेकिन 80 दोनों के बाद पता चला कि केवल कि मी सड़क बन पाई है तो काम को समय पर करने के लिए कितने अतिरिक्त मजदुर को काम पर लगाने कि जरुरत है ?
View Solution140 men were employed to finish a piece of work in 80 days. After 50 days 10 more men were employed. After how many days will the work be finished now?
View SolutionA contractor took a contract to finish a work in 80 days. He employed 300 men and after 60 days he had to employ 100 more men and then the work was finished 2 days earlier. By how many days would the work be finished if 100 extra men were not employed?
View Solution120 men can lay a road 80 km long in 20 days. In how many days can 100 men lay a road of length 90 km?
View Solution120 men can lay a road 80 km long in 20 days. In how many days can 100 men lay a road of length 90 km?
View Solutionএকটি সরকারি 100 দিনের কাজের প্রকল্পে 150 জন লোক 25 দিনে 10 কিমি রাস্তা সংস্কার করতে পারে । ওইরূপ 14 কিমি রাস্তা 175 জন লোক কত দিনে সংস্কার করতে পারবে ?
View Solutionएक बिल्डर ने एक फार्महाउस 45 दिन में बनाने का निर्णय लिया। आरंभ में उसने 150 व्यक्ति काम पर लगाये तथा 30 दिन बाद 120 व्यक्ति और काम पर लगाये और कार्य समय से पूरा हो गया। यदि वह अतिरिक्त व्यक्तियों को काम पर नहीं लगाता तो काम निश्चित समय से कितने दिन बाद पूरा होता ?
View SolutionA contractor took a contract to complete a work in 40 days. He initially employed 100 men and after 35 days, he employed 100 more and completed the work on time. If that extra person had not employed then after how many days would the work have been finished after the right time?
View SolutionIf 20 engineers and 20 workers can together construct a 20 km road in 20 days. 40 engineers and 40 workers together construct 40 km road in how many days?
View SolutionIf 20 engineers and 20 workers can together construct a 20 km road in 20 days. 40 engineers and 40 workers together construct 40 km road in how many days?
View SolutionA contract is to be completed in 50 days and 105 men were
set to work, each working 8 h a day. After 25 days, 2/5 th of
the work is finished. How many additional men be employed,
so that the work may be completed on time, each man now
working 9 h a day?
View SolutionA contract to be completed in 56 days and 104 men were set towork each working 8 hours a day. After 30 days, 2/5th of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day?
View SolutionA contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?
View Solution100 workers finish a work in 20, days. How many workers are required to finish the work in 25 days ?
View Solutionएक ठेकेदार ने किसी काम को 40 दिन में खत्म करने के लिये 100 आदमी को काम पर लगा दिया, 35 दिन बाद 100 और आदमियों को काम पर लगाया तो काम खत्म हुआ। अगर ये 100 और आदमी नहीं लगाये होते तो काम कितने दिन में खत्म होता?
View SolutionSanjay took a contract to finish a work in 32 days 8 workers were absent from the beginning and rest of the workers completed the whole work in 36 days. How many laborers were initially employed?
View Solution36 workmen are employed to finish a certain work in 48 days. But it is found that in 24 days only 2/5 work is done. How many more men must be employed to finish the work in time?
View Solutionएक बिल्डर ने एक फार्महाउस 20 दिन में पूरा कराने का निर्णय लिया। आरंभ में उसने 40 व्यक्ति काम पर लगाये तथा 10 दिन बाद 20 व्यक्ति और काम पर लगाये और कार्य समय से पूरा हो गया। यदि वह अतिरिक्त व्यक्तियों को काम पर नहीं लगाता तो काम निश्चित समय से कितने दिन बाद पूरा होता?
View Solution100 मजदूर एक कार्य को 20 दिनों में समाप्त करते हैं। इसी काम को 25 दिन में समाप्त करने हेतु कितने मजदूर लगाने होंगे ?
View Solution