A certain number of men can do a work in 15 days working 8 hours a days.If the number of men is decreased 13, then in how many days can twice the previous work be completed by the remaining men working 5 hours per day?
The correct Answer is:72 days
To solve the problem step by step, we will use the concept of work done, which can be expressed using the formula:
Men×Days×Hours=Work
Step 1: Determine the total work done by the original number of men.
Let the number of men be X. The work done in the original scenario can be calculated as follows:
- Number of days = 15
- Number of hours per day = 8
So, the total work W1 can be expressed as:
W1=X×15×8
Step 2: Calculate the new number of men after the decrease.
The number of men is decreased by 13. Therefore, the new number of men M2 is:
M2=X−13X=23X
Step 3: Determine the total work to be done in the new scenario.
We need to complete twice the previous work, so:
W2=2W1=2(X×15×8)
Step 4: Set up the equation for the new scenario.
Now, we need to find out how many days D2 it will take for the remaining men to complete this work while working 5 hours a day. The equation can be set up as follows:
M2×D2×H2=W2
Substituting the known values:
(23X)×D2×5=2(X×15×8)
Step 5: Simplify the equation.
Now, we can simplify the equation:
23X×D2×5=2×15×8×X
Dividing both sides by X (assuming X≠0):
23D2×5=2×15×8
Now, we can simplify further:
103D2=2×15×8
Calculating the right side:
103D2=240
Step 6: Solve for D2.
Now, multiply both sides by 310:
D2=240×310=72
Conclusion:
The remaining men can complete twice the previous work in 72 days.
---
Let the number of men be X. The work done in the original scenario can be calculated as follows:
- Number of hours per day = 8
W1=X×15×8
The number of men is decreased by 13. Therefore, the new number of men M2 is:
M2=X−13X=23X
We need to complete twice the previous work, so:
W2=2W1=2(X×15×8)
Now, we need to find out how many days D2 it will take for the remaining men to complete this work while working 5 hours a day. The equation can be set up as follows:
M2×D2×H2=W2
Substituting the known values:
(23X)×D2×5=2(X×15×8)
Now, we can simplify the equation:
23X×D2×5=2×15×8×X
Dividing both sides by X (assuming X≠0):
23D2×5=2×15×8
Now, we can simplify further:
103D2=2×15×8
Calculating the right side:
103D2=240
Now, multiply both sides by 310:
D2=240×310=72
The remaining men can complete twice the previous work in 72 days.
Topper's Solved these Questions
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-1)33videos
TIME AND WORK PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-2)20videos
TIME AND WORK PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK PIPES AND CISTERNSEXERCISE - Short Answer Type Questions15videos
TIME AND WORK PIPES AND CISTERNS
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND DISTANCE EXERCISE - Concept Application (Level 2 )3videos
TIME AND DISTANCE
- BOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORK, PIPES AND CISTERNSEXERCISE - CONCEPT APPLICATION (LEVEL-3)7videos
TIME AND WORK, PIPES AND CISTERNS
Similar Questions
A certain number of men can do a work in 15 days working 8 hours a days.If the number of men is decreased 13, then in how many days can twice the previous work be completed by the remaining men working 5 hours per day?
View SolutionA certain number of men can do a job in 10 days, working 6 hours a day. If the number of men is decreased by 13rd, then in how many days can the remaining men complete the work, working 9 hours per day?
View Solution
Knowledge Check
- Question 1 - Select One
A certain number of people can complete can complete a piece of work in 12 days working 5 hours a day. If thenumber of men is decreased by half, how many hours a day should they work, so that the work is to be completed in 15 days ?
A10B9C8D6 - Question 2 - Select One
A certain number of people can complete can complete a piece of work in 12 days working 5 hours a day. If thenumber of men is decreased by half, how many hours a day should they work, so that the work is to be completed in 15 days ?
A10B9C8D6 - Question 3 - Select One
A certain number of people can complete can complete a piece of work in 12 days working 5 hours a day. If thenumber of men is decreased by half, how many hours a day should they work, so that the work is to be completed in 15 days ?
A10B9C8D6
A certain number of men can do a job in 10 days, working 6 hours a day. If the number of men is decreased by 13rd, then in how many days can the remaining men complete the work, working 9 hours per day?
View SolutionA certain number of men can do a job in 10 days, working 6 hours a day. If the number of men is decreased by 13rd, then in how many days can the remaining men complete the work, working 9 hours per day?
View SolutionIf 36 men can do a piece of work in 25 days, in how many days will 15 men do it?
View SolutionIf 10 men can do a work in 20 days, then how many men can do the same work in 4 days?
(a)60 men
(b)20 men
(c)50 men
(d)40 menView Solution8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
View Solution