A certain number of men can do a work in 15 days working 8 hours a days.If the number of men is decreased 13, then in how many days can twice the previous work be completed by the remaining men working 5 hours per day?

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:72 days


To solve the problem step by step, we will use the concept of work done, which can be expressed using the formula:

Men×Days×Hours=Work

Step 1: Determine the total work done by the original number of men.
Let the number of men be X. The work done in the original scenario can be calculated as follows:

- Number of days = 15
- Number of hours per day = 8

So, the total work W1 can be expressed as:
W1=X×15×8

Step 2: Calculate the new number of men after the decrease.
The number of men is decreased by 13. Therefore, the new number of men M2 is:
M2=X13X=23X

Step 3: Determine the total work to be done in the new scenario.
We need to complete twice the previous work, so:
W2=2W1=2(X×15×8)

Step 4: Set up the equation for the new scenario.
Now, we need to find out how many days D2 it will take for the remaining men to complete this work while working 5 hours a day. The equation can be set up as follows:
M2×D2×H2=W2
Substituting the known values:
(23X)×D2×5=2(X×15×8)

Step 5: Simplify the equation.
Now, we can simplify the equation:
23X×D2×5=2×15×8×X
Dividing both sides by X (assuming X0):
23D2×5=2×15×8
Now, we can simplify further:
103D2=2×15×8
Calculating the right side:
103D2=240

Step 6: Solve for D2.
Now, multiply both sides by 310:
D2=240×310=72

Conclusion:
The remaining men can complete twice the previous work in 72 days.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A certain number of people can complete can complete a piece of work in 12 days working 5 hours a day. If thenumber of men is decreased by half, how many hours a day should they work, so that the work is to be completed in 15 days ?

    A10
    B9
    C8
    D6
  • A certain number of people can complete can complete a piece of work in 12 days working 5 hours a day. If thenumber of men is decreased by half, how many hours a day should they work, so that the work is to be completed in 15 days ?

    A10
    B9
    C8
    D6
  • A certain number of people can complete can complete a piece of work in 12 days working 5 hours a day. If thenumber of men is decreased by half, how many hours a day should they work, so that the work is to be completed in 15 days ?

    A10
    B9
    C8
    D6