8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
2
3
4
5
The correct Answer is:C
Step by step video, text & image solution for 8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Similar Questions
12 men can complete a work within 9 days. After 3 days they started the work, 6 men joined them to replace 2 men. How many days will they take to complete the remaining work?
View SolutionTwelve men can complete a work in 8 days. Three days after they started the work, 3 more men joined them. In how many days will all of them together complete the remaining work ?
View Solution
Knowledge Check
- Question 1 - Select One
A can finish a work in 12 days and B can do it in 15 days. ’After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?
A3B4C5D6 - Question 2 - Select One
A can finish a work in 12 days and B can do it in 15 days. After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?
A3B4C5D6 - Question 3 - Select One
A can finish a work in 12 days and B can do it in 15 days. ’After A had worked for 3 days, B also joined A to finish the remaining work. In how many days, the remaining work will be finished?
A5B512C412D6
18 men can complete a work in 9 days. After they have worked for 5 days, 6 more men join them. How many days will they take to complete the remaining work ?
18 पुरुष किसी कार्य को 9 दिनों में पूरा कर सकते हैं | उनके 5 दिनों तक कार्य कर लेने के बाद, 6 अतिरिक्त पुरुष उनके साथ हो गए | शेष कार्य करने में उन्हें कितना समय लगेगा ?View Solution24 men can complete a piece of work in 15 days. 2 days after
the 24 men started working, 4 men left the work. How
many more days will the remaining men now take to
complete the remaining work?View Solution24 man can complete a piece of work in 15 days. 2 days after
the 24 men started working, 4 men left the work. How many
more days will the remaining men now take to complete the
remaining work?View Solution14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work ?
View Solution45 men can complete a work in 16 days. Four days after they started working, 36 more men joined them. How many days will they now take to complete the remaining work?
View Solution