76 ladies complete a job in 33 days.Due to some reason some ladies did not join the work and therefore it was completed in 44 days. The number of ladies who did not report for the work is
22
21
20
19
The correct Answer is:D
Step by step video, text & image solution for 76 ladies complete a job in 33 days.Due to some reason some ladies did not join the work and therefore it was completed in 44 days. The number of ladies who did not report for the work is by Maths experts to help you in doubts & scoring excellent marks in Class 9 exams.
Updated on:21/07/2023Topper's Solved these Questions
- IMO QUESTION PAPER SET B 2019BOOK - SCIENCE OLYMPIAD FOUNDATION CHAPTER - IMO QUESTION PAPER SET B 2019EXERCISE - ACHIEVERS SECTION
5 Videos
- IMO QUESTION PAPER SET B 2019BOOK - SCIENCE OLYMPIAD FOUNDATION CHAPTER - IMO QUESTION PAPER SET B 2019EXERCISE - MATHEMATICAL REASONING
18 Videos
- IMO QUESTION PAPER SET A 2019BOOK - SCIENCE OLYMPIAD FOUNDATION CHAPTER - IMO QUESTION PAPER SET A 2019EXERCISE - Achievers Section
5 Videos
- INTRODUCTION TO EUCLID'S GEOMETRYBOOK - SCIENCE OLYMPIAD FOUNDATION CHAPTER - INTRODUCTION TO EUCLID'S GEOMETRYEXERCISE - Achievers Section (HOTS)
3 Videos
Similar Questions
Two workers 'A' and 'B' working together completed a job in 5 days. Had 'A' worked twice as efficiently as he actually did, the work would have completed in 3 days. In how many days could 'A' alone complete the job ?
View SolutionA and B can complete a job in 24 days working together. A alone can complete it in 32 days. Both of them worked together for 8 days and then A left. The number of days B will take to complete the remaining job is
View Solution
Knowledge Check
A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:
A100B110C55D50A work could be completed in 100 days by some workers. However, due to the absence of 10 workers, it was completed in 110 days. The original number of workers was:
A100B110C55D5035 boys can do a piece of work in 15 days. The work will completed in 25 days. How many boys did not turn up for the job?
A14B20C6D7
A certain numner of men agreed to do a work in 20 days. 5 men did come for work. Others completed the work in 40 days. Find the number of men who had agreed to do the work originally.
View SolutionA man completes a job in 15 days. His son completes the same job in 10 days. If both work together then in how many days the work will be completed ?
View SolutionA worker has to complete a job of 175 units. On each day starting from the second, he does 75% of the part of the job he did on the previous day. Find the number of days in which the job is completed if he did 36 units of work on the 3rd day.
View SolutionX can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in
View Solution16 men finished one-third work in 6 days. The number of additional men are required to complete the job in next 6 days :
View Solution