A worker has to complete a job of 175 units. On each day starting from the second, he does 75% of the part of the job he did on the previous day. Find the number of days in which the job is completed if he did 36 units of work on the 3rd day.
3
4
5
6
The correct Answer is:B
Let the work done on the first day be x.
Then the work done on the third day =34×34x which is equal to 36 units
Topper's Solved these Questions
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 3
21 Videos
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 1
30 Videos
- BANKING AND COMPUTINGBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - BANKING AND COMPUTINGEXERCISE - Level 3
6 Videos
Similar Questions
A man starts a job, working at the rate of 1 unit a day. After each day, another man joins the working group. The man who joins on the xth day of the job works until the job is completed, at x units per day.The job is completed in 4 days. The time the man who started the work would have taken to complete the job alone is (in days) :
View SolutionA group of workers having equal efficiency can complete a job in 4 days. But it so happened that every alternate day starting from the second day, 3 workers are withdrawn from the job and every alternate day starting from the third day, 2 workers are added to the group. If it now takes 7 days to complete the job, find the number of workers who started the job. 4 b. 5 c. 6 d. 8
View Solution
Knowledge Check
If 40 men can complete a job in 6 days, then find the number fo days taken by 60 men to complete it.
A3B10C12D4A and B can complete a job in 24 days working together. A alone can complete it in 32 days. Both of them worked together for 8 days and then A left. The number of days B will take to complete the remaining job is
A16B32C64D128Shantanu completes 5/8 of a job in 20 days. At this rate, how many more days will he take to finish the job ?
A6 daysB18 daysC5 daysD12 days
76 ladies complete a job in 33 days.Due to some reason some ladies did not join the work and therefore it was completed in 44 days. The number of ladies who did not report for the work is
View SolutionTheere are 5 men in group. Each man can complete a job in 35 days. One of them starts it . Starting from the second day, a man joins until the 5th day. Therefore, all the men work together. Find the total time taken to complete the job. ( in days)
View Solution33 men can do a job in 30 days. If 44 men started the job together and after every day of the work, one person leaves. What is the minimum number of days required to complete the whole work?
View Solution33 men can do a job in 30 days. If 44 men started the job together and after every day of the work, one person leaves. What is the minimum number of days required to complete the whole work?
View Solution15 men take 20 days to com plete a job working 8 hours a day. The number of hours a day should 20 men take to complete the job in 12 days
View Solution