27 men can dig a well in 20 days working 5 hours a day. They start digging it. After 4 days, 12 men leave. How hourse a day should the remaining men work to complete digging it by the scheduled date ?
6
8
10
9
The correct Answer is:D
Let the requred number of hours pe day b h.
Let the work done by each man be 1 unit/hr /
The time for which 27 men worked in the first our days =(5)(4) hours =20 hours
Work complete in the first 4 days =(27)(1)(20) units =540 units
Renaining in time =(20−4)(h) hours =16 h hours.
Completed in the remaining time =(27−12)(1)(16h) units =240 h units
Total time taken =(5)(20) hours=100 hours
Total work =(27)(1)(100) units =2700 units 2700+540+240h
9 hours
Topper's Solved these Questions
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 3
21 Videos
- TIME AND WORKBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - TIME AND WORKEXERCISE - LEVEL 1
30 Videos
- BANKING AND COMPUTINGBOOK - PEARSON IIT JEE FOUNDATIONCHAPTER - BANKING AND COMPUTINGEXERCISE - Level 3
6 Videos
Similar Questions
Thirty men can dig a well in 10 days on working 8 hours a day. They started the work but after 2 days, 10 men left. How many hours a day should the remaining men work to complete it on time?
View Solution8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
View Solution
Knowledge Check
If 4 men can reap a field in 5 days working 12 hours a day, in how many days can 10 men reap the same field working 8 hours a day?
A3B2C4D68 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?
A2B3C4D58 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finIsh the work. In how many days would the remaining work be completed?
A2B3C4D5
A certain number of men can do a job in 10 days, working 6 hours a day. If the number of men is decreased by 13rd, then in how many days can the remaining men complete the work, working 9 hours per day?
View SolutionA certain number of men can do a job in 10 days, working 6 hours a day. If the number of men is decreased by 13rd, then in how many days can the remaining men complete the work, working 9 hours per day?
View Solution10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days.
View Solution10 men, working. 6 hours a day can compJete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days?
View SolutionA certain number of people can complete can complete a piece of work in 12 days working 5 hours a day. If thenumber of men is decreased by half, how many hours a day should they work, so that the work is to be completed in 15 days ?
View Solution