Seventy-five men are employed to lay down a railway line in 3 months. Due to certain emergency conditions, the work was to be finished in 18 days. How many more men should be employed to complete the work in the desired time ?
300
325
350
375
The correct Answer is:A
To solve the problem, we will use the concept of man-days, which is a way to measure the amount of work done by a certain number of men in a given number of days.
1. Determine the total work in man-days:
- We know that 75 men can complete the work in 3 months.
- First, convert months to days. Assuming 1 month = 30 days, then 3 months = 3 × 30 = 90 days.
- Therefore, the total work in man-days = Number of men × Number of days = 75 men × 90 days = 6750 man-days.
2. Calculate the required work to be done in the new time frame:
- The work needs to be completed in 18 days.
- Let M2 be the number of men required to complete the work in 18 days.
- The equation for the total work remains the same: M2×18 days=6750 man-days.
3. Solve for M2:
- Rearranging the equation gives us M2=6750 man-days18 days.
- Calculating this gives M2=375 men.
4. Determine how many more men are needed:
- Initially, there were 75 men employed.
- The additional men required = Total men required - Initial men = 375−75=300.
Final Answer:
Therefore, 300 more men should be employed to complete the work in the desired time of 18 days.
---
- We know that 75 men can complete the work in 3 months.
- First, convert months to days. Assuming 1 month = 30 days, then 3 months = 3 × 30 = 90 days.
- Therefore, the total work in man-days = Number of men × Number of days = 75 men × 90 days = 6750 man-days.
- The work needs to be completed in 18 days.
- Let M2 be the number of men required to complete the work in 18 days.
- The equation for the total work remains the same: M2×18 days=6750 man-days.
- Rearranging the equation gives us M2=6750 man-days18 days.
- Calculating this gives M2=375 men.
- Initially, there were 75 men employed.
- The additional men required = Total men required - Initial men = 375−75=300.
Therefore, 300 more men should be employed to complete the work in the desired time of 18 days.
Similar Questions
20 men complete one- third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days? 10 b. 12 c. 15 d. 20
View SolutionTwenty two men can complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
View Solution
Knowledge Check
40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
A12B20C18D2420 men complete one- third of a piece of work in 20 days. How many more men should be employed to finish the rest of the work in 25 more days? 10 b. 12 c. 15 d. 20
A10B12C15D20Twenty two men cann complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
A45B60C57D80
Twenty two men cann complete a piece of work in 17 days. They work for 2 days. How many more men should now be employed so as to complete the work in another 10 days?
View Solution20 men complete one-third of a work in 20 days. How may more men should be employed to finish the rest of th ework in 25 more days ?
View SolutionTwenty five men can make a certain number of chairs in 80 working hours. They work for 10 hours. How many more men should now be employed so as to complete the work in another 50 working hours?
View SolutionTwenty five men can make a certain number of chairs in 80 working hours. They work for 10 hours. How many more men should now be employed so as to complete the work in another 50 working hours?
View Solution60 men could complete a work in 250 days. They worked together for 200 days. After that the work had to be stopped for 10 days due to bad weather. How many more men should be engaged to complete the work in time?
View Solution