'A' can complete a work in 20 days while B is 25% more efficient than A. B worked for 6 days and left. The remaining work is completed by Cin 15 days. Find in how many days C can complete the whole work alone.
27 days
21 days
18 days
24 days
The correct Answer is:D
To solve the problem, we need to determine how many days C can complete the whole work alone. Let's break down the solution step by step.
Step 1: Determine A's work rate
A can complete the work in 20 days. Therefore, A's work rate is:
Work rate of A=120 (work per day)
Step 2: Determine B's work rate
B is 25% more efficient than A. To find B's work rate, we first calculate 25% of A's work rate:
25% of A's work rate=0.25×120=180
Now, we add this to A's work rate to find B's work rate:
Work rate of B=120+180
To add these fractions, we need a common denominator, which is 80:
Work rate of B=480+180=580=116 (work per day)
Step 3: Calculate the work done by B in 6 days
Now, we calculate how much work B completes in 6 days:
Work done by B in 6 days=6×116=616=38
Step 4: Determine the remaining work
The total work is considered as 1 unit. Therefore, the remaining work after B has worked for 6 days is:
Remaining work=1−38=58
Step 5: Calculate C's work rate
C completes the remaining work in 15 days. Therefore, C's work rate can be calculated as:
Work rate of C=Remaining workTime taken by C=5815=5120=124 (work per day)
Step 6: Determine how many days C can complete the whole work alone
To find out how many days C can complete the whole work alone, we take the reciprocal of C's work rate:
Days taken by C to complete the whole work=1124=24 days
Final Answer
C can complete the whole work alone in 24 days.
A can complete the work in 20 days. Therefore, A's work rate is:
Work rate of A=120 (work per day)
B is 25% more efficient than A. To find B's work rate, we first calculate 25% of A's work rate:
25% of A's work rate=0.25×120=180
Now, we add this to A's work rate to find B's work rate:
Work rate of B=120+180
To add these fractions, we need a common denominator, which is 80:
Work rate of B=480+180=580=116 (work per day)
Now, we calculate how much work B completes in 6 days:
Work done by B in 6 days=6×116=616=38
The total work is considered as 1 unit. Therefore, the remaining work after B has worked for 6 days is:
Remaining work=1−38=58
C completes the remaining work in 15 days. Therefore, C's work rate can be calculated as:
Work rate of C=Remaining workTime taken by C=5815=5120=124 (work per day)
To find out how many days C can complete the whole work alone, we take the reciprocal of C's work rate:
Days taken by C to complete the whole work=1124=24 days
C can complete the whole work alone in 24 days.
Similar Questions
A can complete a work in 20 days and B in 30 days. A worked alone for 4 days and then B completed the remaining work along with C in 18 days . In how many days can C working alone complete the work ?
View SolutionA can do a piece of work in 12 days and B in 20 days. If they together work on it for 5 days, and remaining work is completed by C in 3 days, then in how many days can C do the same work alone?
View Solution
Knowledge Check
X' can complete a work in 40 days while Y is 20% more effi-
cient then 'X' .'Y' worked for 8 days and lift, remaining work is
completed by 'Z' in 20 days. Find in how many days 'Z' can ltbegt complete the whole work alone?A27 daysB21 daysC18 daysD26 daysA and B together can complete a work in 10 days. They started together but A left after 2 days and the remaining work was completed by B in 12 days. In how many days can A complete the entire work while working alone?
A15B20C30D45A and B together can complete a work in 20 days. They started together but after 4 days A left the work. The remaining work was completed by B alone in 24 more days. In how many days can A complete the entire work alone?
A75B25C45D60
NiNAl can alone complete a work in 20 days. Suresh is 25% more efficient than her. He can complete the work in __ days.
View SolutionA can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?
View SolutionA can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?
View SolutionA and B together can complete a work in 15 days. They started together but after 5 days A left the work. If the remaining work is completed by B in 15 more days, then A alone can complete the entire work in how many days?
View SolutionA and B together can complete a work in 15 days. They started together but after 5 days A left the work. If the remaining work is completed by B in 15 more days, then A alone can complete the entire work in how many days?
View Solution