A project requires 12 women to complete it in 16 days. 12 women started working and after a few days from the start of the project, 4 women left. If the remaining project was completed in 18 days, in how many days was the whole project completed?
24'12
26
22
21'12
The correct Answer is:C
Step by step video, text & image solution for A project requires 12 women to complete it in 16 days. 12 women started working and after a few days from the start of the project, 4 women left. If the remaining project was completed in 18 days, in how many days was the whole project completed? by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.
Updated on:21/07/2023Similar Questions
Three men or five women can complete a piece of work in 8 days. In how many days can 6 men and 6 women complete it?
View Solution25 men and 15 women can complete the work in 12 days. They started working together and after 8 days, women left the work. Now 25 men complete the remaining work in 6 days. Find the time required to complete the work by only 15 women?
View Solution
Knowledge Check
Five men or ten women can complete a job in 20 days. In how many days can 3 men and 4 women complete it ?
A10B15C20D25Five men or ten women can complete a job in 20 days. In how many days can 3 men and 4 women complete it ?
A10B15C20D2521 typist can complete a task in 8 days. Then in how many days 15 typist can complete that task?
21 टाइपिस्ट 8 दिनों में एक कार्य पूरा कर सकता है। फिर 15 टाइपिस्ट कितने दिनों में उस कार्य को पूरा करेंगे ?A5.8B11.2C9.3D7
25 men and 15 women can complete a piece of work in 12 days. All of them start working together and after working for 8 days, the women stopped working 25 men completed the remaining work in 6 days. How many days will it take for completing the entire job, if only 15 women are put on the job?
View Solution25 men and 15 women can complete a piece of work in 12 days. All of them start working together and after working for 8 days, the women stopped working 25 men completed the remaining work in 6 days. How many days will it take for completing the entire job, if only 15 women are put on the job?
View SolutionA and B together can complete a work in 10 days. They started together but A left after 2 days and the remaining work was completed by B in 12 days. In how many days can A complete the entire work while working alone?
View Solution24 women can complete a work in 45 days. If 18 women are employed, then in how many days the work would be completed?
View Solution24 women can complete a work in 45 days. If 18 women are employed, then in how many days the work would be completed?
View Solution