Doubtnut Promotions Sticky

25 men and 15 women can complete a piece of work in 12 days. All of them start working together and after working for 8 days, the women stopped working 25 men completed the remaining work in 6 days. How many days will it take for completing the entire job, if only 15 women are put on the job?

A

48 days

B

24 days

C

36 days

D

60 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will follow the logical sequence of calculations based on the information provided.

Step 1: Determine the total work done by 25 men and 15 women in 12 days.

Let the efficiency of one man be M and the efficiency of one woman be W.

The total work done by 25 men and 15 women in 12 days can be expressed as:
Total Work=(25M+15W)×12

Step 2: Calculate the work done in the first 8 days by both men and women.

In the first 8 days, all 25 men and 15 women worked together:
Work done in 8 days=(25M+15W)×8

Step 3: Determine the remaining work after 8 days.

After 8 days, the remaining work is:
Remaining Work=Total WorkWork done in 8 days

Step 4: Calculate the work done by 25 men in the next 6 days.

After the first 8 days, only the 25 men continue to work for 6 more days:
Work done by 25 men in 6 days=25M×6

Step 5: Set up the equation for total work.

Now, we can equate the total work done to the sum of the work done in the first 8 days and the work done in the next 6 days:
(25M+15W)×12=(25M+15W)×8+25M×6

Step 6: Simplify the equation.

Expanding both sides:
300M+180W=200M+120W+150M
300M+180W=350M+120W

Step 7: Rearranging the equation.

Rearranging gives:
180W120W=350M300M
60W=50M

Step 8: Find the ratio of women's efficiency to men's efficiency.

From the equation 60W=50M:
WM=5060=56

This means the efficiency of one woman is 5 and the efficiency of one man is 6.

Step 9: Calculate the total work done.

Now, we can calculate the total work done:
Total Work=(25×6+15×5)×12
Calculating the efficiencies:
=(150+75)×12=225×12=2700 units of work

Step 10: Determine how long it will take for 15 women to complete the work.

The efficiency of 15 women is:
15W=15×5=75 units of work per day

Now, to find the number of days D it will take for 15 women to complete the total work:
D=Total WorkEfficiency of 15 women=270075=36 days

Final Answer:
It will take 36 days for 15 women to complete the entire job.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    25 men and 15 women can complete the work in 12 days. They started working together and after 8 days, women left the work. Now 25 men complete the remaining work in 6 days. Find the time required to complete the work by only 15 women?

    A36 days
    B88 days
    C94 days
    DNone of these
  • Question 2 - Select One

    9 women con complete a piece of work in 19 days. How
    many days will 18 women take to complete the same piece of
    work ?

    A12 days
    B6.5 days
    C9 days
    DNone of these
  • Question 3 - Select One

    15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

    A40
    B42
    C38
    D32