Ratio of efficiency of A and B in completing a work is 3 : 4. Both started to work together but A left after 2 days. Another person C joins B and they together complete the remaining work in 6 days. If A and B together can complete the work in 8 days then C alone can complete the work in how many days?
A)274days
B)563days
C)413days
D)283days
The correct Answer is:B
To solve the problem step by step, let's break down the information given and find the required solution.
Step 1: Understand the Efficiency Ratio
The efficiency ratio of A and B is given as 3:4. This means:
- Let the efficiency of A = 3 units
- Let the efficiency of B = 4 units
Step 2: Calculate Total Efficiency of A and B
The combined efficiency of A and B when they work together is:
Efficiency of A + Efficiency of B=3+4=7 units
Step 3: Calculate Total Work
It is given that A and B together can complete the work in 8 days. Therefore, the total work can be calculated as:
Total Work=Combined Efficiency×Time=7 units×8 days=56 units
Step 4: Work Done by A and B in 2 Days
When A and B work together for 2 days, the amount of work done is:
Work Done=Combined Efficiency×Time=7 units×2 days=14 units
Step 5: Remaining Work
The remaining work after A leaves is:
Remaining Work=Total Work−Work Done=56 units−14 units=42 units
Step 6: Work Done by B and C Together
B continues to work and is joined by C. They complete the remaining work in 6 days. The combined efficiency of B and C is:
Let the efficiency of C be c units. Then:
Efficiency of B + Efficiency of C=4+c
The work done by B and C together in 6 days is:
Work Done=Combined Efficiency×Time=(4+c)×6
Setting this equal to the remaining work:
(4+c)×6=42
Step 7: Solve for C's Efficiency
Expanding the equation:
24+6c=42
Now, isolate c:
6c=42−24
6c=18
c=3 units
Step 8: Calculate Time Taken by C Alone
Now we need to find out how many days C will take to complete the entire work alone. The time taken by C to complete the work is given by:
Time=Total WorkEfficiency of C=56 units3 units=563 days
Final Answer
C alone can complete the work in 563 days.
---
The efficiency ratio of A and B is given as 3:4. This means:
- Let the efficiency of A = 3 units
- Let the efficiency of B = 4 units
The combined efficiency of A and B when they work together is:
Efficiency of A + Efficiency of B=3+4=7 units
It is given that A and B together can complete the work in 8 days. Therefore, the total work can be calculated as:
Total Work=Combined Efficiency×Time=7 units×8 days=56 units
When A and B work together for 2 days, the amount of work done is:
Work Done=Combined Efficiency×Time=7 units×2 days=14 units
The remaining work after A leaves is:
Remaining Work=Total Work−Work Done=56 units−14 units=42 units
B continues to work and is joined by C. They complete the remaining work in 6 days. The combined efficiency of B and C is:
Let the efficiency of C be c units. Then:
Efficiency of B + Efficiency of C=4+c
Work Done=Combined Efficiency×Time=(4+c)×6
(4+c)×6=42
Expanding the equation:
24+6c=42
6c=42−24
6c=18
c=3 units
Now we need to find out how many days C will take to complete the entire work alone. The time taken by C to complete the work is given by:
Time=Total WorkEfficiency of C=56 units3 units=563 days
C alone can complete the work in 563 days.
Topper's Solved these Questions
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PREVIOUS YEAR QUESTIONS
32 Videos
- TIME AND WORK & PIPE AND CISTERN BOOK - ADDA247CHAPTER - TIME AND WORK & PIPE AND CISTERN EXERCISE - PRELIMS QUESTIONS (LEVEL - 2)
40 Videos
- SPEED, TIME AND DISTANCEBOOK - ADDA247CHAPTER - SPEED, TIME AND DISTANCEEXERCISE - Previous Year Questions
31 Videos
Similar Questions
A alone can complete a work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work?
View SolutionA and B together can complete a piece of work in 4 days. If A alone can complete the same work in 12 days, in how many days can B alone complete that work ?
View Solution
Knowledge Check
A alone can complete a piece of work in 12 days. A and B together can complete it in 8 days. How long will B alone take to complete the work ?
A18 daysB24 daysC16 daysD20 daysBoth A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
A30B50C45D42Both A and B together can complete a work in 20 days and B alone can complete the same work in 36 days. In how many days will A alone complete the work?
A30B50C45D42
A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View SolutionA is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View SolutionA and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
View SolutionIn how many days will B alone complete the work?
I. A and B together can complete the work in 8 days. II. B and C together can complete the work in 10 days.
III. A and C together can complete the work in 12 days
View SolutionA alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?
View Solution