A can do a work in 5 days while B can do the same work in 8 days. They worked together to complete the work and earned Rs. 6760. Find A's share ?
Rs. 5070
Rs. 3600
Rs. 4160
Rs. 4056
The correct Answer is:C
To solve the problem, we need to determine A's share of the total earnings based on the amount of work done by A and B together.
1. Determine Work Rates:
- A can complete the work in 5 days. Therefore, A's work rate is:
Work rate of A=1 work5 days=15 work per day
- B can complete the work in 8 days. Therefore, B's work rate is:
Work rate of B=1 work8 days=18 work per day
2. Calculate Combined Work Rate:
- When A and B work together, their combined work rate is:
Combined work rate=15+18
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 5 and 8 is 40.
- Convert the fractions:
15=840,18=540
- Now add them:
Combined work rate=840+540=1340 work per day
3. Calculate Total Work:
- Since A and B together can complete the work at a rate of 1340 work per day, the total work can be considered as 1 unit of work.
- The time taken to complete the work together is:
Time=1 work1340 work per day=4013 days
4. Calculate Individual Contributions:
- In 4013 days, the amount of work done by A is:
Work done by A=Work rate of A×Time=15×4013=813 of the work
- The amount of work done by B is:
Work done by B=Work rate of B×Time=18×4013=513 of the work
5. Calculate A's Share of Earnings:
- The total earnings are Rs. 6760. A's share of the earnings is proportional to the work done by A:
A's share=Total Earnings×Fraction of work done by A
A's share=6760×813=4160
Final Answer:
A's share of the earnings is Rs. 4160.
- A can complete the work in 5 days. Therefore, A's work rate is:
Work rate of A=1 work5 days=15 work per day
- B can complete the work in 8 days. Therefore, B's work rate is:
Work rate of B=1 work8 days=18 work per day
- When A and B work together, their combined work rate is:
Combined work rate=15+18
- To add these fractions, we need a common denominator. The least common multiple (LCM) of 5 and 8 is 40.
- Convert the fractions:
15=840,18=540
- Now add them:
Combined work rate=840+540=1340 work per day
- Since A and B together can complete the work at a rate of 1340 work per day, the total work can be considered as 1 unit of work.
- The time taken to complete the work together is:
Time=1 work1340 work per day=4013 days
- In 4013 days, the amount of work done by A is:
Work done by A=Work rate of A×Time=15×4013=813 of the work
- The amount of work done by B is:
Work done by B=Work rate of B×Time=18×4013=513 of the work
- The total earnings are Rs. 6760. A's share of the earnings is proportional to the work done by A:
A's share=Total Earnings×Fraction of work done by A
A's share=6760×813=4160
A's share of the earnings is Rs. 4160.
Similar Questions
Knowledge Check
A alone can do a piece of work in 3 days, while B alone can do the same work in 2 days. If they work together to complete the work, their total wages is fixed 225. Find the share of A.
A90B75C95D65P alone can complete the work in 5 days,Q alone can do same work in 6 days and R alone can do the same work in 12 days. They jointly complete the work and earn Rs. 5400. What is the share of R?
A1000B1200C1500D1800P alone can complete the work in 5 days,Q alone can do same work in 6 days and R alone can do the same work in 12 days. They jointly complete the work and earn Rs. 5400. What is the share of R?
A1000B1200C1500D1800
P alone can complete the work in 5 days,Q alone can do same work in 6 days and R alone can do the same work in 12 days. They jointly complete the work and earn Rs. 5400. What is the share of R?
View SolutionA can do a work in 20 days and B can do the same work in 30 days in how many days canA and B together do the work?
View SolutionKrishna can do a work in 10 days while Mohan can do the same work in 20 days. They started work together. After 3 days Krishna left the work and Mohan completed it. For how many days Mohan worked alone more than the number of days required when both worked together ?
View SolutionA can do 13 of a work in 30 days. B can do 25 of the same work in 24 days. They worked together for 20 days. C completed the remaining work in 8 days. Working together A, B and C will complete the same work in:
View SolutionA can do 25 of a work in 12 days while B can do 6623% of the same work in 16 days. They work together for 10 days. B alone will complete the remaining work in
View Solution