S and T can finish a work in 50 days. They worked together for 20 days and then left . How much of the work is left

A

3/5

B

1/3

C

1/2

D

2/5

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we need to determine how much work S and T have completed together in 20 days and how much work is left after that.

1. Determine the Total Work:
Since S and T can finish the work together in 50 days, we can assume that the total work is equivalent to 1 unit of work per day. Therefore, the total work can be represented as:
Total Work=50 units

2. Calculate Work Done in 20 Days:
If S and T can complete the entire work in 50 days, then in 1 day, they complete:
Work done in 1 day=1 unit50 days=150 units
In 20 days, the work done by S and T together will be:
Work done in 20 days=20×150=2050=25 units

3. Calculate the Remaining Work:
To find out how much work is left after they have worked for 20 days, we subtract the work done from the total work:
Remaining Work=Total WorkWork Done
Remaining Work=5025 units
To perform this subtraction, we need to convert 50 into a fraction with a denominator of 5:
50=2505
Now we can subtract:
Remaining Work=250525=25025=2485 units

4. Final Answer:
The amount of work left after S and T have worked together for 20 days is:
Remaining Work=2485 units49.6 units

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • Vikram and Vivek can finish a work in 50 days. They worked together for 20 days and then left. How much work has been done by them?

    A3/5
    B1/3
    C1/2
    D2/5
  • A and B can together finish a work in 30 days. They worked together for 20 days and then B left. After another 20 days. A finished the remaining work. In how many days A alone can finish the job?

    A50 days
    B60 days
    C48 days
    D54 days
  • A can do a piece of work in 25 days and B can do the same work in 30 days. They work together for 5 days, how much of work is left?

    A1130
    B1530
    C1930
    D1230