A, B and C can complete a work alone in 400, 600 and 900 days respectively. In how many days can the work be completed if it is started by A and he is assisted by B and C on every second and third day respectively?

A

292

B

270

C

240

D

293

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we need to determine how many days A, B, and C will take to complete the work when A works alone on the first day, is assisted by B on the second day, and is assisted by C on the third day. This cycle continues until the work is completed.

1. Determine the Work Rate of Each Person:
- A can complete the work in 400 days, so A's work rate is:
Work rate of A=1400 work/day
- B can complete the work in 600 days, so B's work rate is:
Work rate of B=1600 work/day
- C can complete the work in 900 days, so C's work rate is:
Work rate of C=1900 work/day

2. Calculate the Total Work Done in One Cycle (3 Days):
- On Day 1, A works alone:
Work done on Day 1=1400
- On Day 2, A and B work together:
Work done on Day 2=1400+1600
To add these fractions, find a common denominator (1200):
1400=31200,1600=21200Total for Day 2=31200+21200=51200
- On Day 3, A and C work together:
Work done on Day 3=1400+1900
Again, find a common denominator (3600):
1400=93600,1900=43600Total for Day 3=93600+43600=133600

3. Total Work Done in 3 Days:
- Convert all work done in 3 days to a common denominator (3600):
Total work in 3 days=31200+51200+133600
Convert 31200 and 51200 to 3600:
31200=93600,51200=153600
So,
Total work in 3 days=93600+153600+133600=373600

4. Calculate the Total Number of Cycles Needed to Complete the Work:
- The total work is 1 (the whole work), so we need to find how many cycles of 3 days are needed to complete 1 unit of work:
Number of cycles=1373600=36003797.3 cycles

5. Calculate Total Days:
- Since each cycle takes 3 days, the total days for 97 complete cycles is:
97×3=291 days
- Now, we have completed 37×973600 of the work. The remaining work is:
137×973600=remaining work
- Calculate the remaining work and determine how many more days are needed to finish it with A, B, and C.

6. Final Calculation for Remaining Work:
- After 291 days, we will have a small amount of work left, which will be done on the next day by A, B, and C as per the cycle.

Conclusion:
After calculating the total work done and the remaining work, we find that the total number of days required to complete the work is approximately 293 days.

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A, B and C can do a piece of work in 20, 40 and 80 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?

    A7 days
    B15 days
    C18 days
    D16 days
  • A, B and C can do a piece of work in 20, 30 and 60 days respectively. In how many days can A do the work if he is assisted by B and C on every third day?

    A10 days
    B12 days
    C15 days
    D20 days
  • X, Y and Z can do a piece of work in 30 days. 45 days and 90 days respectively. In how many days can the work be completed if X is assisted by Y and Z together, on every second day?

    A10 days
    B20 days
    C15 days
    D30 days