Doubtnut Promotions Sticky

B is thrice as efficient as A and C is 0.75 times as efficient as A. What is the ratio of number of days taken by A, B and C when they work individually?
A. 4:1:3
B. 3:1:4
C. 2:3:1
D. 5:1:2

A

C

B

A

C

D

D

B

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:D

|
Answer

Step by step video, text & image solution for B is thrice as efficient as A and C is 0.75 times as efficient as A. What is the ratio of number of days taken by A, B and C when they work individually? A. 4:1:3 B. 3:1:4 C. 2:3:1 D. 5:1:2 by Maths experts to help you in doubts & scoring excellent marks in Class 14 exams.

Updated on:21/07/2023

Similar Practice Problems

  • Question 1 - Select One

    A is thrice efficient as B and C is twice as efficient as B. What is the ratio of number of days taken by A, B and C, when the work individually?

    A2:6:3
    B2:3:6
    C2:6:3
    D3:1:2
  • Question 1 - Select One

    The efficiency of work of P and Q are in the ratio 5 : 7. What will be the ratio of number of days taken by them to finish the work?
    A. 7:5
    B. 3:4
    C. 4:3
    D. 5:7

    AA
    BD
    CB
    DC
  • Question 1 - Select One

    A is thrice as efficient as B and hence completes a work in 40
    days less than the number days taken by B. What will be
    the number of days taken by both of them when working
    together ?

    A22.5 days
    B15 days
    C20 days
    D18 days
  • Question 1 - Select One

    A is thrice as efficient as B. Working together they complete the work in 3 days. If B takes 8 days more than A, what is the number of days taken by A to finish the whole work, alone ?

    A4
    B2
    C12
    D16
  • Question 1 - Select One

    The ratio of efficiency of A is to C is 5:3. The ratio of number of days taken by B is to C is 2:3. A takes 6 days less than C, when A and C completes the work individually. B and C started the work and left after 2 days. The number of days taken by A to finish the remaining work is :

    A4.5
    B5
    C6
    D913
  • Question 1 - Select One

    The ratio of efficiency of A is to C is.5 :3 The ratio of number of days taken by B is to C is 2:3 . A takes 6 days less than C, when A and C completes the work individually. B and C started the work arid left after 3 days. The number of days taken by A to finish the remaining work is:

    A4.5
    B5
    C6
    D913
  • Question 1 - Select One

    A is twice as efficient as B and B is thrice as efficient as C. Working together, they can finish a certain work in 5 days. If A and C worked together for 5 days then B alone would complete the remaining work in .......

    A8 days
    B5 days
    C6 days
    D4 days

Similar Questions