A can do a work in 30 days B can complete same work in 20 days and A+B+C can do a work in 10 days . find in how many days C can complete the same work ?
60
50
40
30
The correct Answer is:B
To solve the problem step by step, we will first determine the work rates of A, B, and C, and then find out how long it will take for C to complete the work alone.
Step 1: Determine the work rates of A and B
- A can complete the work in 30 days. Therefore, A's work rate is:
Work rate of A=130 (work per day)
- B can complete the work in 20 days. Therefore, B's work rate is:
Work rate of B=120 (work per day)
Step 2: Determine the combined work rate of A, B, and C
- A, B, and C together can complete the work in 10 days. Therefore, their combined work rate is:
Combined work rate of A, B, and C=110 (work per day)
Step 3: Set up the equation for C's work rate
- The combined work rate can also be expressed as the sum of the individual work rates:
Work rate of A+Work rate of B+Work rate of C=Combined work rate
130+120+Work rate of C=110
Step 4: Solve for C's work rate
- Let the work rate of C be represented as 1C. The equation becomes:
130+120+1C=110
- To isolate 1C, we first need to find a common denominator for the fractions on the left side. The least common multiple (LCM) of 30, 20, and 10 is 60.
Step 5: Rewrite the fractions with a common denominator
- Converting each fraction:
130=260,120=360,110=660
- Substitute these values back into the equation:
260+360+1C=660
Step 6: Combine the fractions
- Combine the fractions on the left:
560+1C=660
Step 7: Isolate 1C
- Subtract 560 from both sides:
1C=660−560=160
Step 8: Solve for C
- Taking the reciprocal gives us:
C=60
Conclusion
C can complete the work alone in 60 days.
- A can complete the work in 30 days. Therefore, A's work rate is:
Work rate of A=130 (work per day)
- B can complete the work in 20 days. Therefore, B's work rate is:
Work rate of B=120 (work per day)
- A, B, and C together can complete the work in 10 days. Therefore, their combined work rate is:
Combined work rate of A, B, and C=110 (work per day)
- The combined work rate can also be expressed as the sum of the individual work rates:
Work rate of A+Work rate of B+Work rate of C=Combined work rate
130+120+Work rate of C=110
- Let the work rate of C be represented as 1C. The equation becomes:
130+120+1C=110
- To isolate 1C, we first need to find a common denominator for the fractions on the left side. The least common multiple (LCM) of 30, 20, and 10 is 60.
- Converting each fraction:
130=260,120=360,110=660
- Substitute these values back into the equation:
260+360+1C=660
- Combine the fractions on the left:
560+1C=660
- Subtract 560 from both sides:
1C=660−560=160
- Taking the reciprocal gives us:
C=60
C can complete the work alone in 60 days.
Similar Questions
A can do a work in 10 days B can do the same work in 20 days if both start the work together and A leaves 5 days before the end of the work then in how many days the total work is completed
View SolutionA किसी काम को 30 दिन में कर लेता है और B उसी काम को 60 दिन में कर लेता है। दोनों मिलकर उस काम को कितने दिन में करेंगे?
View SolutionA and B can do a piece of work in 8 days, B and C can do the same work in 12 days and A, B and C together can do it in 6 days. In how many days will A and C together complete it?
View SolutionA can do a piece of work in 20 days and B can do the same work in 30 days. In how many days will both complete the work?
View SolutionA and B can do a piece of work in 15 days. B and C can do the same work in 12 days and C and A can do it in 10 days. How many days will A take to complete the work by himself?
View SolutionA, B and C together can do a piece of work in 20 days. A and B can complete the same work in 30 days. In how many days alone can complete the work?
View SolutionA, B and C can do a piece of work in 5, 20 and 60 days respectively. Working together, in how many days can they complete the same work?
View SolutionA and B can do a piece of work in 8 days, B and C can do the same work in 12 days. If A, B and C can complete the same work in 6 days, in how many days can A and C complete the same work?
View Solution