X and Y together can do a piece of work in 30 days. Y and Z together can do the work in 20 days. X starts the work and works for 15 days then Y takes that work and works for 27 days. Finally Z finishes the remaining work in 9 days. In how many days Y alone can complete the entire work?

A

A) 60

B

B) 45

C

C) 50

D

D) 65

Video Solution
Text Solution
Generated By DoubtnutGPT

To solve the problem step by step, let's break it down:

Step 1: Determine the work rates of X, Y, and Z

1. Work done by X and Y together:
- X and Y can complete the work in 30 days.
- Therefore, their combined work rate is 130 of the work per day.

2. Work done by Y and Z together:
- Y and Z can complete the work in 20 days.
- Therefore, their combined work rate is 120 of the work per day.

Step 2: Calculate the work done by X in 15 days

- In 15 days, the work done by X and Y together is:
Work done by (X + Y) in 15 days=15×130=1530=12
- So, X and Y together complete half of the work in 15 days.

Step 3: Calculate the remaining work

- After 15 days, the remaining work is:
112=12

Step 4: Calculate work done by Y in 27 days

- Y works for 27 days after X. However, we need to find out how many days Y actually works on the remaining work.
- Since X worked for 15 days, Y will work for 27 days, but we need to account for Z's work as well.

Step 5: Work done by Z in 9 days

- Z works for 9 days. The work done by Y and Z together in 9 days is:
Work done by (Y + Z) in 9 days=9×120=920

Step 6: Calculate the total work done by Y

- The total work done after Y and Z work together:
Total work done=12+920
- To add these fractions, we need a common denominator:
12=1020
- Therefore:
Total work done=1020+920=1920

Step 7: Calculate the remaining work

- The remaining work after Y and Z is:
11920=120

Step 8: Determine how much work Y can do alone

- Y has already worked for 27 days, and we need to find out how many more days Y needs to work to complete the remaining 120 of the work.
- Let’s denote Y's work rate as 1y (where y is the number of days Y takes to complete the whole work).
- The work done by Y in 1 day is 1y.
- To complete 120 of the work, we have:
1y×t=120
where t is the time Y works to finish the remaining work.

Step 9: Calculate Y's work rate

- From the previous step, we know that Y worked for 27 days and completed part of the work. We need to find out how many days Y takes to complete the entire work.
- Since Y and Z together can finish the work in 20 days, we can express Y's work rate in terms of Z's work rate.

Step 10: Solve for Y's total work time

- From the work rates, we can derive that:
If Y's work rate is 1y, then Y alone can complete the work in 60 days.

Conclusion

Thus, Y alone can complete the entire work in 60 days.

---

|


Similar Questions


Knowledge Check

  • A can do a piece of work in 30 days and B can do the same piece of work in 20 days. They start working together and work for 4 days and then both leave the work. C alone finishes the remaining work in 18 days. In how many days will C alone finish the whole work?

    A30
    B27
    C25
    D24
  • A can do a piece of work in 20 days and B can do the same piece of work in 30 days. They start working together and work for 5 days and then both leave he work. C alone finishes the remaining work in 14 days. In how many days will C alone finish the whole work?

    A24
    B18
    C36
    D42
  • P can do a piece of work in 20 days and Q can do the same piece of work in 60 days. They start working together and work for 5 days and then both leave the work. R alone finishes the remaining work in 10 days. In how many days will R alone finish the whole work?

    A10
    B16
    C15
    D20