18 men can do 3 units of work in 10 days by doing 8 hours in a day. Then find the required number of days taken by 10 men to complete 5 units of work if they work 6 hours in a day
32 days
45 days
36 days
40 days
The correct Answer is:D
To solve the problem step by step, we will use the relationship between men (m), days (d), time (t), and work (w). The formula we will use is:
m1⋅d1⋅t1w1=m2⋅d2⋅t2w2
Step 1: Identify the given values
From the problem, we have:
- m1=18 men
- d1=10 days
- t1=8 hours/day
- w1=3 units of work
We need to find:
- m2=10 men
- t2=6 hours/day
- w2=5 units of work
- d2=? (the number of days we need to find)
Step 2: Substitute the known values into the formula
Substituting the known values into the formula gives:
18⋅10⋅83=10⋅d2⋅65
Step 3: Simplify the left side
Calculating the left side:
18⋅10⋅83=14403=480
So, we have:
480=10⋅d2⋅65
Step 4: Simplify the right side
Now, simplify the right side:
10⋅d2⋅65=2⋅d2⋅6=12d2
Step 5: Set the two sides equal
Now we have:
480=12d2
Step 6: Solve for d2
To find d2, divide both sides by 12:
d2=48012=40
Conclusion
The required number of days taken by 10 men to complete 5 units of work, working 6 hours a day, is 40 days.
From the problem, we have:
- m1=18 men
- d1=10 days
- t1=8 hours/day
- w1=3 units of work
- m2=10 men
- t2=6 hours/day
- w2=5 units of work
- d2=? (the number of days we need to find)
Substituting the known values into the formula gives:
Calculating the left side:
Now, simplify the right side:
Now we have:
To find d2, divide both sides by 12:
The required number of days taken by 10 men to complete 5 units of work, working 6 hours a day, is 40 days.
Similar Questions
12 men can complete a work in 30 days by working 9 hours a day. What is the number of men required to complete 10 times of this work in 24 days by working 5 hours a day ?
View SolutionFifteen men can complete a piece of work in 10 days, working 8 hours per day. How many persons are required to complete double the work in 25 days, working 6 hours per day ?
View Solution
Knowledge Check
Working 7 hours in a day, 4 men can do a piece of work in 8 days. Working 8 hours in a day, the required number of men to perform the same work in 4 days will be
A1. 8B2. 4C3. 7D4. 9Fifteen men take 30 days to complete a piece of work, working 8 hours a day. Find the time taken by 30 men to complete 5 times as much work, working 10 hours a day.
A30 daysB45 daysC60 daysD15 days36 personn working 8 hours a day can do 3 units of working in 12 days. How many persons are required to complete 4 units of that work, if they work 6 hours a day for 16 days?
A50B55C48D45
24 persons working 8 hours a day can complete 2 units of a work in 10 days. How many persons are required to complete 4 units of that work, if they work 6 hours a day for 16 days?
एक दिन में 8 घंटे कार्य करते हुए 24 व्यक्ति किसी कार्य की 2 इकाई 10 दिनों में समाप्त कर सकते हैं | इस कार्य की 4 इकाई समाप्त करने के लिए कितने लोगों की आवश्यकता होगी यदि वे 16 दिनों तक एक दिन में 6 घंटे कार्य करते हैं ?
View SolutionIf 10 men can complete a piece of work in 12 days by working 7 hours a day, then in how many days can 14 mendo the same work by working 6 hours a day?
View SolutionIf 15 men can complete a work in 16 days by working 8 hours daily, then in how many days will 10 men complete the work by working 12 hours daily?
View Solution18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
View Solution18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
View Solution