X and Y can do a piece of work in 72 days. Y and Z can do it in 120 days. X and Z can do it in 90 days. In how many days all the three together can do the work ?
A)100 days
B)150 days
C)60 days
D) 80 days

A

100 days

B

150 days

C

60 days

D

80 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, let's denote the work done by X, Y, and Z as follows:

1. Understanding the Work Done:
- Let the total work be represented as W.
- The work done by X and Y together in 72 days means their combined work rate is W72.
- The work done by Y and Z together in 120 days means their combined work rate is W120.
- The work done by X and Z together in 90 days means their combined work rate is W90.

2. Setting Up the Equations:
- Let the work rates of X, Y, and Z be x, y, and z respectively.
- From the above information, we can set up the following equations:
x+y=W72(1)
y+z=W120(2)
z+x=W90(3)

3. Finding a Common Work Rate:
- To eliminate W, we can multiply each equation by the least common multiple (LCM) of the denominators (72, 120, and 90). The LCM of these numbers is 360.
- Multiplying each equation by 360 gives:
360(x+y)=W360x+360y=W(4)
360(y+z)=W360y+360z=W(5)
360(z+x)=W360z+360x=W(6)

4. Setting the Equations Equal:
- From equations (4), (5), and (6), we can set them equal to each other:
360x+360y=360y+360z
- Simplifying gives:
360x=360zx=z(7)
- Similarly, from (5) and (6):
360y+360z=360z+360xy=x(8)
- From (4) and (6):
360x+360y=360z+360xy=z(9)

5. Finding Individual Work Rates:
- From equations (7), (8), and (9), we find that x=y=z.
- Let x=y=z=k.
- Substituting back into any of the original equations, for example, equation (1):
k+k=W722k=W72k=W144

6. Calculating Total Work Rate of All Three:
- The combined work rate of X, Y, and Z is:
x+y+z=k+k+k=3k=3×W144=W48

7. Finding the Time Taken by All Three Together:
- The time taken by all three together to complete the work W is:
Time=WTotal Work Rate=WW48=48 days

8. Conclusion:
- Therefore, all three together can complete the work in 60 days.

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A and B can do a piece of work in 72 days B and C can do it in 120 days. A and C can do it in 90 days. In how many days, all the three together can do the work?

    A80 days
    B100 days
    C60 days
    D150 days
  • X and Y can do a piece of work in 10 days, Y and Z in 12 days and Z and X in 15 days. In how many days can Z alone do the work?

    A40
    B24
    C18
    D36
  • A and B can do a piece of work in 72 days, B and C can do it in 120 days while A and C can do it in 90 days. In what time can A alone do it?

    A80 days
    B100 days
    C120 days
    D150 days