A can do some work in 24 days, B can do it in 32 days and C can do it in 60 days. They start working together. A left after 6 days and B left after working for 8 days. How many more days are required to complete the whole work?
A)30
B)25
C)22
D)20
30
25
22
20
The correct Answer is:C
To solve the problem step by step, we will calculate the work done by A, B, and C, and then determine how many more days are required to complete the work after A and B leave.
Step 1: Calculate the work done by A, B, and C in one day.
- A can complete the work in 24 days, so A's work in one day = 124.
- B can complete the work in 32 days, so B's work in one day = 132.
- C can complete the work in 60 days, so C's work in one day = 160.
Step 2: Find the combined work done by A, B, and C in one day.
To find the total work done by A, B, and C together in one day, we add their individual work rates:
Total work in one day=124+132+160
To add these fractions, we need to find a common denominator. The least common multiple (LCM) of 24, 32, and 60 is 480.
Now, convert each fraction:
124=20480,132=15480,160=8480
Adding these together:
Total work in one day=20+15+8480=43480
Step 3: Calculate the work done in the first 6 days.
In 6 days, the total work done by A, B, and C is:
Work done in 6 days=6×43480=258480
Step 4: Calculate the work done by A and B in the next 2 days.
After 6 days, A leaves, and B continues to work for 2 more days (totaling 8 days). In these 2 days, A and B work together:
Work done by A in 6 days=6×124=624=14
Work done by B in 8 days=8×132=832=14
Work done by C in 8 days=8×160=860=215
Now, we need to add the work done by A, B, and C in the first 8 days:
Total work done in 8 days=14+14+215
Convert to a common denominator (LCM of 4 and 15 is 60):
14=1560,14=1560,215=860
Adding these:
Total work done in 8 days=15+15+860=3860=1930
Step 5: Calculate the total work done after 8 days.
Now, we need to find the total work done after 8 days:
Total work done=258480+3860
Convert 3860 to a denominator of 480:
3860=38×860×8=304480
Now add:
Total work done=258+304480=562480
Step 6: Calculate the remaining work.
The total work is 1 (or 480480). The remaining work is:
Remaining work=1−562480=480−562480=−82480
Step 7: Calculate how many days C needs to finish the remaining work.
C will finish the remaining work alone. C's work rate is 160 per day.
To find how many days C needs to complete the remaining work:
Days required by C=Remaining workC's work rate=82480160=82×60480=4920480=10.25 days
Final Step: Total days required to complete the work.
After A and B left, C needs approximately 10.25 days to finish the work alone.
Final Answer:
The total number of days required to complete the work after A and B left is approximately 10.25 days.
- B can complete the work in 32 days, so B's work in one day = 132.
- C can complete the work in 60 days, so C's work in one day = 160.
Work done by B in 8 days=8×132=832=14
Work done by C in 8 days=8×160=860=215
Topper's Solved these Questions
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Standard Level)
37 Videos
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Expert Level)
27 Videos
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Test Yourself
15 Videos
- SET THEORYBOOK - DISHA PUBLICATIONCHAPTER - SET THEORYEXERCISE - Test Yourself
15 Videos
- TIME, SPEED AND DISTANCEBOOK - DISHA PUBLICATIONCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - Test Yourself
15 Videos
Similar Questions
A can do a work in 20 days and B can do it in 14 days. If they work together for 7 days, then the fraction of the work left is:
View SolutionA can do a piece of work in 8 days, B can do it in 16 days, while C can do it in 80 days. In how many days they can complete the whole work, working together?
View Solution
Knowledge Check
A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it?
A70 daysB4234 daysC2717daysD1717 daysA can do 40% of a work in 6 days and B can do 30% of the same work in 3 days. They started the work together but B left after 2 days and A continued to work. In how many days was the entire work completed ?
A किसी कार्य का 40% भाग 6 दिनों में तथा B इसी कार्य का 30% भाग 3 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य शुरू किया लेकिन 2 दिनों के बाद B हट गया और A ने कार्य जारी रखा | पूरा कार्य कितने दिनों में समाप्त हुआ ?A10B12C9D15A can do a work in 40 days and B can do the same work in 60 days. In how many days they can do it together?
A12B10C15D24
A can do a piece of work in 10 days, B can do it in 12 days and C can do it in 15 days. In how many days they can complete the work, working together?
View SolutionA and B can do a piece of work in 72 days B and C can do it in 120 days. A and C can do it in 90 days. In how many days, all the three together can do the work?
View SolutionA can do a work in 45 days and B can do it in 40 days. Both starts the work together and after some days Aleaves the work. If the work is completed in 32 days, then for how many days A worked?
View SolutionA and B can do a work in 8 days. B alone can do it in 24 days. In how many days, A alone can do the same work?
View SolutionA can do a work in 20 days. B can do a work in 30 days and C can do a work in 60 days. If 'B' and 'C' helps A every third day, then how many days after work will complete?
View Solution