A can do some work in 24 days, B can do it in 32 days and C can do it in 60 days. They start working together. A left after 6 days and B left after working for 8 days. How many more days are required to complete the whole work?
A)30
B)25
C)22
D)20

A

30

B

25

C

22

D

20

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will calculate the work done by A, B, and C, and then determine how many more days are required to complete the work after A and B leave.

Step 1: Calculate the work done by A, B, and C in one day.

- A can complete the work in 24 days, so A's work in one day = 124.
- B can complete the work in 32 days, so B's work in one day = 132.
- C can complete the work in 60 days, so C's work in one day = 160.

Step 2: Find the combined work done by A, B, and C in one day.

To find the total work done by A, B, and C together in one day, we add their individual work rates:

Total work in one day=124+132+160

To add these fractions, we need to find a common denominator. The least common multiple (LCM) of 24, 32, and 60 is 480.

Now, convert each fraction:

124=20480,132=15480,160=8480

Adding these together:

Total work in one day=20+15+8480=43480

Step 3: Calculate the work done in the first 6 days.

In 6 days, the total work done by A, B, and C is:

Work done in 6 days=6×43480=258480

Step 4: Calculate the work done by A and B in the next 2 days.

After 6 days, A leaves, and B continues to work for 2 more days (totaling 8 days). In these 2 days, A and B work together:

Work done by A in 6 days=6×124=624=14
Work done by B in 8 days=8×132=832=14
Work done by C in 8 days=8×160=860=215

Now, we need to add the work done by A, B, and C in the first 8 days:

Total work done in 8 days=14+14+215

Convert to a common denominator (LCM of 4 and 15 is 60):

14=1560,14=1560,215=860

Adding these:

Total work done in 8 days=15+15+860=3860=1930

Step 5: Calculate the total work done after 8 days.

Now, we need to find the total work done after 8 days:

Total work done=258480+3860

Convert 3860 to a denominator of 480:

3860=38×860×8=304480

Now add:

Total work done=258+304480=562480

Step 6: Calculate the remaining work.

The total work is 1 (or 480480). The remaining work is:

Remaining work=1562480=480562480=82480

Step 7: Calculate how many days C needs to finish the remaining work.

C will finish the remaining work alone. C's work rate is 160 per day.

To find how many days C needs to complete the remaining work:

Days required by C=Remaining workC's work rate=82480160=82×60480=4920480=10.25 days

Final Step: Total days required to complete the work.

After A and B left, C needs approximately 10.25 days to finish the work alone.

Final Answer:

The total number of days required to complete the work after A and B left is approximately 10.25 days.

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do a piece of work in 30 days while B can do it in 40 days. In how many days can A and B working together do it?

    A70 days
    B4234 days
    C2717days
    D1717 days
  • A can do 40% of a work in 6 days and B can do 30% of the same work in 3 days. They started the work together but B left after 2 days and A continued to work. In how many days was the entire work completed ?
    A किसी कार्य का 40% भाग 6 दिनों में तथा B इसी कार्य का 30% भाग 3 दिनों में पूरा कर सकता है | उन्होंने एक साथ कार्य शुरू किया लेकिन 2 दिनों के बाद B हट गया और A ने कार्य जारी रखा | पूरा कार्य कितने दिनों में समाप्त हुआ ?

    A10
    B12
    C9
    D15
  • A can do a work in 40 days and B can do the same work in 60 days. In how many days they can do it together?

    A12
    B10
    C15
    D24