Sakshi can do a piece of work in 20 days. Tanya is 25% more efficient than Sakshi. The number of days taken by Tanya to do the same piece of work is
(a)15
(b)16
(c)18
(d)25

A

15

B

16

C

18

D

25

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem, we need to determine how many days Tanya will take to complete the same piece of work that Sakshi can do in 20 days, given that Tanya is 25% more efficient than Sakshi.

1. Determine Sakshi's Efficiency:
- Sakshi can complete the work in 20 days.
- Therefore, Sakshi's work efficiency can be calculated as:
Efficiency of Sakshi=1 work20 days=120 work per day

Hint: Efficiency is calculated as the total work divided by the number of days taken to complete that work.

2. Calculate Tanya's Efficiency:
- Tanya is 25% more efficient than Sakshi.
- To find Tanya's efficiency, we first calculate 25% of Sakshi's efficiency:
25% of Sakshi's efficiency=0.25×120=180
- Now, we add this to Sakshi's efficiency to find Tanya's efficiency:
Efficiency of Tanya=120+180
- To add these fractions, we need a common denominator (which is 80):
120=480(since 20×4=80)
- Now we can add:
Efficiency of Tanya=480+180=580=116 work per day

Hint: When adding fractions, ensure you have a common denominator.

3. Calculate the Number of Days Tanya Takes:
- Since Tanya's efficiency is 116 work per day, the number of days Tanya will take to complete the work is the reciprocal of her efficiency:
Days taken by Tanya=1 work116 work per day=16 days

Hint: The number of days taken to complete a work is the inverse of the efficiency.

Conclusion:
Thus, the number of days taken by Tanya to do the same piece of work is 16 days.

Final Answer:
(b) 16

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A can do a piece of work in 24 days. If B is 60% more efficient than A, then the number of days required by B to do the same piece of work is :

    A10
    B15
    C12
    D9.6
  • A can do a certain job in 12 days. B in 60% more efficient than A. What is the number of days it takes B to do the same piece of work ?

    A712
    B614
    C8
    D6
  • A can do a piece of work in 24 days. If B is 60% more efficient than A, then the number of days required by B to do the same piece of work is :

    A10
    B15
    C12
    D9.6