10 men can complete a piece of work in 15 days and 15 women can complete the same work in 12 days. If all the 10 men and 15 women work together, in how many days will the work get completed?
6
The correct Answer is:C
To solve the problem step by step, we will first determine the work done by the men and women individually, and then combine their efforts to find out how long it will take them to complete the work together.
Step 1: Determine the total work in terms of units.
Given that 10 men can complete the work in 15 days, we can calculate the total work in units.
- Total work = Number of men × Days × Work done per day by each man.
- Let's assume the total work is 60 units (as derived from the LCM approach in the video).
Step 2: Calculate the work done by 10 men in one day.
- Work done by 10 men in 15 days = 60 units.
- Therefore, work done by 10 men in 1 day = Total work / Days = 60 units / 15 days = 4 units.
Step 3: Calculate the work done by 15 women in one day.
Given that 15 women can complete the same work in 12 days:
- Work done by 15 women in 12 days = 60 units.
- Therefore, work done by 15 women in 1 day = Total work / Days = 60 units / 12 days = 5 units.
Step 4: Calculate the combined work done by 10 men and 15 women in one day.
- Combined work done in one day = Work done by 10 men + Work done by 15 women = 4 units + 5 units = 9 units.
Step 5: Calculate the total number of days required to complete the work together.
- Total work = 60 units.
- Work done in one day = 9 units.
- Therefore, number of days required = Total work / Work done in one day = 60 units / 9 units = 6.67 days, which can be expressed as 6 complete 2/3 days.
Final Answer:
The work will be completed in 6 complete 2/3 days.
---
Given that 10 men can complete the work in 15 days, we can calculate the total work in units.
- Let's assume the total work is 60 units (as derived from the LCM approach in the video).
- Work done by 10 men in 15 days = 60 units.
- Therefore, work done by 10 men in 1 day = Total work / Days = 60 units / 15 days = 4 units.
Given that 15 women can complete the same work in 12 days:
- Therefore, work done by 15 women in 1 day = Total work / Days = 60 units / 12 days = 5 units.
- Combined work done in one day = Work done by 10 men + Work done by 15 women = 4 units + 5 units = 9 units.
- Total work = 60 units.
- Work done in one day = 9 units.
- Therefore, number of days required = Total work / Work done in one day = 60 units / 9 units = 6.67 days, which can be expressed as 6 complete 2/3 days.
The work will be completed in 6 complete 2/3 days.
Topper's Solved these Questions
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Standard Level)
37 Videos
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Expert Level)
27 Videos
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Test Yourself
15 Videos
- SET THEORYBOOK - DISHA PUBLICATIONCHAPTER - SET THEORYEXERCISE - Test Yourself
15 Videos
- TIME, SPEED AND DISTANCEBOOK - DISHA PUBLICATIONCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - Test Yourself
15 Videos
Similar Questions
10 men can complete a piece of work in 15 days and 15 women can complete the same work in 12 days. If all the 10 men and 15 women work together, how many days will the work get completed ? a. 6 b. 613 c. 623 d. 723
View Solution24 men can complete a piece of work in 16 days and 18 women can complete the same work in 32 days. 12 men and 6 women work together for 16 days. If the remaining work was to be completed in 2 days, how many additional men would be required besisdes 12 men and 6 women ?
View Solution
Knowledge Check
15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
A40B42C38D3212 men can complete a work in 16 days and 16 women can complete the same work in 12 days In how many days will 4 men and 8 women complete that work ?
A16B12C18D103 men can do a piece of work in 6 days. 5 women can do the same work in 18 days. If 4 men and 10 women work together, then how long will it take to finish the work?
A3 daysB5 daysC2 daysD4 days
If 10 men can complete a work in 12 days . In how many days can 18 men complete the same work ?
View Solution4 men and 6 women can complete a work in 8 days, While 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it.
View Solution4 men and 6 women can complete a work in 8 days, while 3 men and 7 women can complete it in 10 days. In how many days will 10 women complete it?
View SolutionTen men or twelve women can finish the same work in 10 days. If 5 men and 2 women undertake the work together, how many days will they take to complete the work?
दस पुरुष या बारह महिलाएं एक कार्य को 10 दिनों में पूरा कर सकती हैं | यदि 5 पुरुष तथा 2 महिलाओं ने उस कार्य को शुरू किया, तो कार्य पूरा करने में उन्हें कितने दिन लगेंगे ?
View SolutionIf 15 men can complete a work in 48 days, then how many men required to complete the same work in 30 days ?
View Solution