5 men working 8 hours a day can completely build a wall of length 20 metres, breadth 14 metre and height 6 metres in 3 days. How many days will 8 men working 6 hours a day require to build a wall of length 120 meters, breadth 12 metre and height 4 metres.

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:20 days.


To solve the problem, we will use the concept of work done, which can be expressed in terms of men, days, and hours. We will denote the work done in the first scenario and use it to find the time required in the second scenario.

1. Calculate the Work Done in the First Scenario:
- The dimensions of the wall are:
- Length (L1) = 20 meters
- Breadth (B1) = 1/4 meters
- Height (H1) = 6 meters
- The volume of the wall (which represents the work done) can be calculated as:
W1=L1×B1×H1=20×14×6=30 cubic meters

2. Determine the Total Man-Hours in the First Scenario:
- Number of men (M1) = 5
- Number of days (D1) = 3
- Number of hours worked per day (H1) = 8
- Total man-hours (M1 × D1 × H1):
Total Man-Hours=M1×D1×H1=5×3×8=120 man-hours

3. Calculate Work Done Per Man-Hour:
- Work done per man-hour can be calculated as:
Work per man-hour=W1Total Man-Hours=30120=14 cubic meters per man-hour

4. Calculate the Work Required in the Second Scenario:
- The dimensions of the new wall are:
- Length (L2) = 120 meters
- Breadth (B2) = 1/2 meters
- Height (H2) = 4 meters
- The volume of the new wall (W2):
W2=L2×B2×H2=120×12×4=240 cubic meters

5. Determine the Total Man-Hours Required for the Second Scenario:
- Number of men (M2) = 8
- Number of hours worked per day (H2) = 6
- Let D2 be the number of days required.
- The total man-hours for the second scenario can be expressed as:
Total Man-Hours=M2×D2×H2=8×D2×6

6. Set Up the Equation:
- The total work done in man-hours for the second scenario must equal the work required:
24014=8×D2×6
- Simplifying the left side:
240×4=960
- Thus, we have:
960=48D2

7. Solve for D2:
- Rearranging gives:
D2=96048=20

Final Answer:
The number of days required for 8 men working 6 hours a day to build the wall is 20 days.

Updated on:8/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A wall of 100 metres can be built by 7 men or 10 women in 10 days. How many days will 14 men and 20 women take to build a wall of 600 metres ?

    A15
    B20
    C25
    D30
  • If 7 men or 10 women can make a 100 meters wall in 10 days, in how many days 14 men and 20 women can make a 600 m wall?

    A15
    B20
    C25
    D30
  • 10 men working 8 hours day can do a work in 30 days. In how many days will 12 men working 4 hours a day take do the same work?

    AA)40 days
    BB)60 days
    CC)50 days
    DD)30 days