5 men working 8 hours a day can completely build a wall of length 20 metres, breadth 14 metre and height 6 metres in 3 days. How many days will 8 men working 6 hours a day require to build a wall of length 120 meters, breadth 12 metre and height 4 metres.
The correct Answer is:20 days.
To solve the problem, we will use the concept of work done, which can be expressed in terms of men, days, and hours. We will denote the work done in the first scenario and use it to find the time required in the second scenario.
1. Calculate the Work Done in the First Scenario:
- The dimensions of the wall are:
- Length (L1) = 20 meters
- Breadth (B1) = 1/4 meters
- Height (H1) = 6 meters
- The volume of the wall (which represents the work done) can be calculated as:
W1=L1×B1×H1=20×14×6=30 cubic meters
2. Determine the Total Man-Hours in the First Scenario:
- Number of men (M1) = 5
- Number of days (D1) = 3
- Number of hours worked per day (H1) = 8
- Total man-hours (M1 × D1 × H1):
Total Man-Hours=M1×D1×H1=5×3×8=120 man-hours
3. Calculate Work Done Per Man-Hour:
- Work done per man-hour can be calculated as:
Work per man-hour=W1Total Man-Hours=30120=14 cubic meters per man-hour
4. Calculate the Work Required in the Second Scenario:
- The dimensions of the new wall are:
- Length (L2) = 120 meters
- Breadth (B2) = 1/2 meters
- Height (H2) = 4 meters
- The volume of the new wall (W2):
W2=L2×B2×H2=120×12×4=240 cubic meters
5. Determine the Total Man-Hours Required for the Second Scenario:
- Number of men (M2) = 8
- Number of hours worked per day (H2) = 6
- Let D2 be the number of days required.
- The total man-hours for the second scenario can be expressed as:
Total Man-Hours=M2×D2×H2=8×D2×6
6. Set Up the Equation:
- The total work done in man-hours for the second scenario must equal the work required:
24014=8×D2×6
- Simplifying the left side:
240×4=960
- Thus, we have:
960=48D2
7. Solve for D2:
- Rearranging gives:
D2=96048=20
Final Answer:
The number of days required for 8 men working 6 hours a day to build the wall is 20 days.
- The dimensions of the wall are:
- Length (L1) = 20 meters
- Breadth (B1) = 1/4 meters
- Height (H1) = 6 meters
- The volume of the wall (which represents the work done) can be calculated as:
W1=L1×B1×H1=20×14×6=30 cubic meters
- Number of men (M1) = 5
- Number of days (D1) = 3
- Number of hours worked per day (H1) = 8
- Total man-hours (M1 × D1 × H1):
Total Man-Hours=M1×D1×H1=5×3×8=120 man-hours
- Work done per man-hour can be calculated as:
Work per man-hour=W1Total Man-Hours=30120=14 cubic meters per man-hour
- The dimensions of the new wall are:
- Length (L2) = 120 meters
- Breadth (B2) = 1/2 meters
- Height (H2) = 4 meters
- The volume of the new wall (W2):
W2=L2×B2×H2=120×12×4=240 cubic meters
- Number of men (M2) = 8
- Number of hours worked per day (H2) = 6
- Let D2 be the number of days required.
- The total man-hours for the second scenario can be expressed as:
Total Man-Hours=M2×D2×H2=8×D2×6
- The total work done in man-hours for the second scenario must equal the work required:
24014=8×D2×6
- Simplifying the left side:
240×4=960
- Thus, we have:
960=48D2
- Rearranging gives:
D2=96048=20
The number of days required for 8 men working 6 hours a day to build the wall is 20 days.
Topper's Solved these Questions
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Foundation Level)
51 Videos
- TIME AND WORKBOOK - DISHA PUBLICATIONCHAPTER - TIME AND WORKEXERCISE - Practice Exercise (Standard Level)
37 Videos
- SET THEORYBOOK - DISHA PUBLICATIONCHAPTER - SET THEORYEXERCISE - Test Yourself
15 Videos
- TIME, SPEED AND DISTANCEBOOK - DISHA PUBLICATIONCHAPTER - TIME, SPEED AND DISTANCEEXERCISE - Test Yourself
15 Videos
Similar Questions
16 workers working 6 hours a day can build a wall of length 150 metres, breadth 20 m and height 12m in 25 days. In how many days 12 workers, working 8 hours a day can build a wall of length 800 m, breadth 15 m and height 6 m.
View SolutionA wall of 100 metres can be built by. 7 men or 10 women in 10 days. How many days will 14 men and 20 women take to build a wall of 600 metres? 15 b. 20 c. 25 d. 30
View Solution
Knowledge Check
A wall of 100 metres can be built by 7 men or 10 women in 10 days. How many days will 14 men and 20 women take to build a wall of 600 metres ?
A15B20C25D30If 7 men or 10 women can make a 100 meters wall in 10 days, in how many days 14 men and 20 women can make a 600 m wall?
A15B20C25D3010 men working 8 hours day can do a work in 30 days. In how many days will 12 men working 4 hours a day take do the same work?
AA)40 daysBB)60 daysCC)50 daysDD)30 days
10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days.
View Solution18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
View Solution18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?
View SolutionHow many men should be employed to build a wall of the same height but of length 26 metres in one day?
View SolutionIf 5 men working 6 hours a day can reap a field in 20 days. In how many days will 15 men reap the field, working 8 hours a day ?
View Solution