S, T and U can complete a work In 40, 48 and 60 days respectively. They received Rs. 10800 to complete the work. They begin the work together but T left 2 days before the completion of the work and U left 5 days before the completion of the work. S has completed the remaining work alone. What is the share of Sin Rs.) from total money?

A

4000

B

4320

C

4500

D

4860

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:D


To solve the problem step by step, we will first determine the work done by each person and then calculate their respective shares from the total money.

Step 1: Determine the work done by S, T, and U
- S can complete the work in 40 days, so S's work rate is 140 of the work per day.
- T can complete the work in 48 days, so T's work rate is 148 of the work per day.
- U can complete the work in 60 days, so U's work rate is 160 of the work per day.

Step 2: Find the LCM of the days to calculate work in units
To find a common unit of work, we will calculate the LCM of 40, 48, and 60.
- The LCM of 40, 48, and 60 is 240.
- Therefore, the total work can be considered as 240 units.

Step 3: Calculate the work done by each person in one day
- S's work in one day = 24040=6 units
- T's work in one day = 24048=5 units
- U's work in one day = 24060=4 units

Step 4: Calculate the total work done by S, T, and U together
- Combined work done in one day by S, T, and U = 6+5+4=15 units.

Step 5: Determine the total time taken to complete the work
Let the total number of days taken to complete the work be x.
- T left 2 days before completion, so T worked for x2 days.
- U left 5 days before completion, so U worked for x5 days.
- S worked for all x days.

The total work equation can be set up as:
6x+5(x2)+4(x5)=240

Step 6: Simplify the equation
Expanding the equation:
6x+5x10+4x20=240
Combining like terms:
15x30=240
Adding 30 to both sides:
15x=270
Dividing by 15:
x=18

Step 7: Calculate the work done by each person
- Work done by S in 18 days = 6×18=108 units.
- Work done by T in 182=16 days = 5×16=80 units.
- Work done by U in 185=13 days = 4×13=52 units.

Step 8: Verify total work done
Total work done = 108+80+52=240 units (which matches the total work).

Step 9: Calculate the share of each person
The total payment is Rs. 10800. The share of each person is proportional to the work done:
- Total units of work = 240
- Value of 1 unit = 10800240=45 Rs.

Step 10: Calculate S's share
- S's share = Work done by S × Value of 1 unit
Ssshare=108×45=4860Rs.

Final Answer:
The share of S from the total money is Rs. 4860.

---

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • S,T and U can complete a work in 40,48 and 60 days respectively. They received Rs. 10800 to complete the work. They begin the work together but T left 2 days before the completion of the work and U left 5 days before the completion of the work. S has completed the remaining work along. What is the share of S ( in Rs. ) from total money ?

    A4000
    B4320
    C4500
    D4860
  • A, B and C can do a piece of work in 20, 24 and 30 days, respectively. They undertook to do the piece of work for Rs. 5400. They begin the work together but B left 2 days before the completion of work and c left 5 days before the completion of work. The share of A from the assured money is

    ARs.2700
    BRs. 540
    CRs. 1800
    DRs. 600
  • A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

    A7310
    B1025
    C10730
    Dnone of these