A man do a work in 12 days working 8 h per day. If he does 6 h per day, what would be the number of days taken by him?
12 days
14 days
16 days
18 days
The correct Answer is:C
To solve the problem step by step, we can follow these instructions:
Step 1: Calculate the total work done
The man works for 12 days, and each day he works for 8 hours.
To find the total work done, we multiply the number of days by the number of hours worked each day.
Total Work=Number of Days×Hours per Day=12days×8hours/day=96hours
Step 2: Determine the number of days required at 6 hours per day
Now that we know the total work is 96 hours, we need to find out how many days it will take if he works 6 hours each day.
We can use the formula:
Number of Days=Total WorkHours per Day
Substituting the values we have:
Number of Days=96hours6hours/day=16days
Conclusion
Thus, if the man works for 6 hours per day, it will take him 16 days to complete the work.
---
The man works for 12 days, and each day he works for 8 hours.
To find the total work done, we multiply the number of days by the number of hours worked each day.
Now that we know the total work is 96 hours, we need to find out how many days it will take if he works 6 hours each day.
Thus, if the man works for 6 hours per day, it will take him 16 days to complete the work.
Similar Questions
50 persons can do a work in 12 days, working 6 h per day. 60 persons can do the same work in 8 days, working x h per days.The value of x is
View SolutionA certain number of men can do a work in 15 days working 8 hours a days.If the number of men is decreased 13, then in how many days can twice the previous work be completed by the remaining men working 5 hours per day?
View Solution
Knowledge Check
40 men can build a wall 200 m long in 12 days, working 8 h a day. What will be the number of days that 30 men will take to build a similar wall 300 m long, working 6 h per day
A32B18C36D918 men can do 3 units of work in 10 days by doing 8 hours in a day. Then find the required number of days taken by 10 men to complete 5 units of work if they work 6 hours in a day
A32 daysB45 daysC36 daysD40 daysA man completes a work in 10 days by doing 5 hours per day. By doing 7 hours per day, he can complete this work in -
A12 daysB10 daysC7 daysDNone of these
2 men and 1 women can complete a piece of work in 14 days, while 4 women and 2 men can do the same work in 8 days . If a man gets Rs. 90 per day , what should be the wages per day of a woman ?
View SolutionA can do a piece of work in 10 days working 8 hours per day. If B is two thirds as efficient as A, then in how many days can B alone do the same piece of work, working 5 hours per day? 15 b. 18 c. 20 d. 24
View SolutionA certain number of people can complete can complete a piece of work in 12 days working 5 hours a day. If thenumber of men is decreased by half, how many hours a day should they work, so that the work is to be completed in 15 days ?
View SolutionA can complete a work in 12 days with a working of 8 hours per day. B can complete the same work in 8 days when working 10 hours a day. If Both start the work together, working 8 hours a day, the work can be completed in __ days.
View SolutionA can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is
View Solution