A man do a work in 12 days working 8 h per day. If he does 6 h per day, what would be the number of days taken by him?

A

12 days

B

14 days

C

16 days

D

18 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we can follow these instructions:

Step 1: Calculate the total work done
The man works for 12 days, and each day he works for 8 hours.
To find the total work done, we multiply the number of days by the number of hours worked each day.

Total Work=Number of Days×Hours per Day=12days×8hours/day=96hours

Step 2: Determine the number of days required at 6 hours per day
Now that we know the total work is 96 hours, we need to find out how many days it will take if he works 6 hours each day.

We can use the formula:

Number of Days=Total WorkHours per Day

Substituting the values we have:

Number of Days=96hours6hours/day=16days

Conclusion
Thus, if the man works for 6 hours per day, it will take him 16 days to complete the work.

---

Updated on:7/8/2024
|


Similar Questions


Knowledge Check

  • 40 men can build a wall 200 m long in 12 days, working 8 h a day. What will be the number of days that 30 men will take to build a similar wall 300 m long, working 6 h per day

    A32
    B18
    C36
    D9
  • 18 men can do 3 units of work in 10 days by doing 8 hours in a day. Then find the required number of days taken by 10 men to complete 5 units of work if they work 6 hours in a day

    A32 days
    B45 days
    C36 days
    D40 days
  • A man completes a work in 10 days by doing 5 hours per day. By doing 7 hours per day, he can complete this work in -

    A12 days
    B10 days
    C7 days
    DNone of these