A and B together can complete a job in 8 days. Both B and C. working alone can finish the same job in 12 days. A and B commence work on the job, and work for 4 days, whereupon A leaves. B continues for 2 more days, and then the he leaves too. C now starts working days did C require?
5
8
3
4
The correct Answer is:D
To solve the problem step by step, we will first determine the work rates of A, B, and C, and then calculate how many days C requires to finish the remaining work after A and B have worked.
Step 1: Determine the work rates of A, B, and C
1. A and B together can complete the job in 8 days.
- Work done by A and B in one day = 1/8 of the job.
2. B and C together can complete the job in 12 days.
- Work done by B and C in one day = 1/12 of the job.
Step 2: Express the work rates
Let:
- Work rate of A = a
- Work rate of B = b
- Work rate of C = c
From the above information:
- a+b=18 (1)
- b+c=112 (2)
Step 3: Find the individual work rates
We can express c in terms of b using equation (2):
- c=112−b
Now substitute c into equation (1):
- a+b=18
- a+b+(112−b)=18+112
Step 4: Find a common denominator and solve for a
The common denominator for 8 and 12 is 24:
- 324+224=524
So, we have:
- a+(112−b)=524
- This simplifies to a+112−b=524
Now, substituting b=18−a:
- a+112−(18−a)=524
Step 5: Solve for a and b
After substituting and simplifying, we can find the values of a and b:
- a=124
- b=18−124=112
Now substituting b back to find c:
- c=112−b=112−112=0
Step 6: Calculate work done by A and B in 4 days
- Work done by A and B in 4 days:
- Work done = 4×(a+b)=4×18=48=12
Step 7: Calculate work done by B in 2 more days
- Work done by B in 2 days:
- Work done = 2×b=2×112=212=16
Step 8: Total work done and remaining work
Total work done by A and B:
- Total work done = 12+16=36+16=46=23
Remaining work:
- Total work = 1 (whole job) - 23=13
Step 9: Calculate how many days C requires to finish the remaining work
Since C's work rate is c=112:
- Days required by C to complete 13 of the work:
- Work done by C in one day = 112
- Days required = Remaining work / C's work rate = 1/31/12=1/3×12/1=4 days.
Final Answer
C requires 4 days to complete the remaining work.
---
- Work done by A and B in one day = 1/8 of the job.
2. B and C together can complete the job in 12 days.
- Work done by B and C in one day = 1/12 of the job.
- Work rate of A = a
- Work rate of B = b
- Work rate of C = c
- a+b=18 (1)
- b+c=112 (2)
- c=112−b
- a+b=18
- a+b+(112−b)=18+112
- 324+224=524
- a+(112−b)=524
- This simplifies to a+112−b=524
- a+112−(18−a)=524
- a=124
- b=18−124=112
- c=112−b=112−112=0
- Work done = 4×(a+b)=4×18=48=12
- Work done = 2×b=2×112=212=16
- Total work done = 12+16=36+16=46=23
- Total work = 1 (whole job) - 23=13
- Days required by C to complete 13 of the work:
- Work done by C in one day = 112
- Days required = Remaining work / C's work rate = 1/31/12=1/3×12/1=4 days.
Similar Questions
(A + B) together can complete a job in 8 days. Both B and C working alone can finish the same job in 12 days. A and B commence work on the job and work for 4 days, where upon A leaves, B continues for 2 more days and then he leaves too, C now starts working and finishes the job, how many days will C require ?
View SolutionP and Q together can do a job in 6 days. Q and R can finish the same job in 60/7 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is
View Solution
Knowledge Check
A and B together can finish a job in 24 days , while A,B and C together can finish can finish the same job in 8 days. C along will finish the job in
A12 daysB14 daysC16 daysD24 daysA and B together can finish a job in 24 days, while A, B and C together can finish the same job in 8 days. C alone will finish the job in
A12 daysB14 daysC16 daysD24 daysA,B and C together can finish a job in 4 days .A and B together can finish the same job in 5 days .In how many days ,C alone will finish the same job ?
A12B16C20D24
X can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in
View SolutionA and B together can do a job in 15 days and A alone could do the same job in 20 days how many days would B take to do half the job if he worked alone
View SolutionP and Q together can do a job in 6 days. Q and R can finish the same job in 607 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is.
View SolutionP and Q together can do a job in 6 days. Q and R can finish the same job in 607 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is.
View SolutionA and B finish a job in 12 days. While A,B and C can finish it in 8 days. C alone will finish the job in-
View Solution