Doubtnut Promotions Sticky

P,Q and R started a piece of work. They worked on it for 5 days, which P left

Text Solution
Verified by Experts

(a) (p+q+r) worked for 5 days, (Q+R) worked for 5 days and R worked for 5 days to complete the work.
(b) P worked for 5 days, Q worked for 10 days and R worked for 15 days to complete the work.(iii) Find the part of the work done by Q and R.
(c ) Then find the part of the work done by P.
(d) Compare them.
When certain people work for the same number of days each, then the ratio of the total work done will be the same as the work done by each of them per day. Hence, if all the people involved work for the same number of days, then the earning can directly be distributed in the ratio of work done per day by each of them . The following example is useful to understand this statement.

Doubtnut Promotions Banner
|
Updated on:21/07/2023

Related Playlists


Knowledge Check

  • Question 1 - Select One

    P and Q can finish a work in 30 days. They worked at it for 10 days and then Q left. The remaining work is done byPalone in 20 more days. How long willPtake to finish the work alone?

    A30 days
    B20 days
    C60 days
    D50 days
  • Question 1 - Select One

    P,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).

    A12
    B18
    C4
    D27
  • Question 1 - Select One

    P,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).

    A12
    B18
    C4
    D27
  • Question 1 - Select One

    A can do a piece of work in 12 days and B in 15 days. They work together for 5 days and then B left. The days taken by A to finish the remaining work is

    A3
    B5
    C10
    D121
  • Question 1 - Select One

    P,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).

    A12
    B18
    C24
    D27
  • Question 1 - Select One

    P,Q and R can do a piece of work in 18 days, 36 days and 54 day respectively. They start the work together but Q and R leave 1 day and 5 days respectively, before the completion of work. In how many days has the work been completed ?

    A10
    B11
    C10711
    D10911
  • Question 1 - Select One

    P,Q and R can do a piece of work in 18 days, 36 days and 54 day respectively. They start the work together but Q and R leave 1 day and 5 days respectively, before the completion of work. In how many days has the work been completed ?

    A10
    B11
    C10711
    D10911
  • Question 1 - Select One

    P,Q and R can do a piece of work in 18 days, 36 days and 54 day respectively. They start the work together but Q and R leave 1 day and 5 days respectively, before the completion of work. In how many days has the work been completed ?

    A10
    B11
    C10711
    D10911
  • Question 1 - Select One

    P and Q undertook a piece of work for ₹ 37500. P alone can do it in 20 days, Q alone can do it in 30 days. With the help of R and P,Q finished the work in 8 days. What is the share of R ?

    A₹ 14000
    B₹ 13000
    C₹12000
    D12500

Similar Questions