P is thrice as good a workman as Q and therfore able to finish a job in 48 days less than Q. working together they can do it in : a 18 days b 24 days c 30 days d 12 days
Correct option a 18 daysExplanation: Total work = No. of days× efficiency = 72×1 = 72 One day work of P and Q is 3+1= 4 units. P+Q will complete the work in = 72/4 = 18 days
Related Solutions
P is thrice as good a workman as Q and therefore able to finish a Job in 48 days less than . Working together, they can do it in :
View SolutionA is thrice as good a workman as B and therefore is able to finish a job in 40 days less than B. Working together, they can do it in
View SolutionA is thrice as good a workman as B and therefore is able to finish a job in 30 days less than B. How many days will they take to finish the job working together?
View SolutionA is thrice as good a workman B and therefore is able to finish a job in 40 days less titan B. Working together, they can do it in
View SolutionA is thrice as good a workman as B and is, therefore, able to finish a piece of work in 60 days less than B. The time (in days) in which they can do it working together is
View SolutionA is thrice as good a workman as B and takes 10 days less to do a piece of work than B takes. The number of days taken by B to finish the work is :
View SolutionA is twice as good a workman as B and together they finish a piece of work in 18 days. In how many days will A alone finish the work?
View SolutionA and B together can do a piece of work in 36 days, B and C together can do it in 24 days. A and C together can do it in 18 days. The three working together can finish the work in
View SolutionP,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).
View SolutionP,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).
View SolutionP,Q and R can complete a job in 18 days,24 days and 36 days respectively. P started it and worked for 3 days. P then left Q then worked on it for 8 days. Q then left. R completed the remaining part of the job in 12 days. Find the time for which R worked (in days).
View SolutionM is thrice as good as workman as N and together they finish a piece of work in 30 days. In how many days will M alone finish the work?
View SolutionA is twice as good a workman as B and is therefore able to finish a piece of work in 30 days less than B. In how many days they can complete the whole work, working together?
View SolutionP and Q together can do a job in days. Q and R can finish the same job in days. P started the work and worked for days. Q and R continued for days. Then the difference of days in which R and P can complete the job is
View SolutionP and Q together can do a job in 6 days. Q and R can finish the same job in days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is.
View SolutionA can do a job in 10 days, B can do the same job in 12 days and C can do the same job in 15 days. In how many days they will finish the work together?
View SolutionSabir is thrice as good as Anish in work. Sabir is able to finish a job in 60 days less than Anish. Both can finish the work in - days working together.
View SolutionSabir is thrice as good as Anish in work. Sabir is able to finish a job in 60 days less than Anish. Both can finish the work in - days working together.
View Solutionयदि A , B तथा C किसी कार्य को अकेले क्रमशः 12 दिन , 15 दिन व् 18 दिन में पूरा करते हैं। यदि तीनों मिलकर इसी कार्य को करना चाहें , तो कार्य कितने दिनों में समाप्त कर सकेंगे ?
View SolutionIf A can do a piece of work in p days and B can do the same in q days: A and B together can finish it in how many days
View Solution