45 men can complete a work in 16 days. Six days after they started working 30 more men joined them. How many days will they now take to complete the remaining work?
45 x 16 men can complete the work in 1 day. 1 mans 1 days work = 1/720 45 mens 6 days work =1/16*6=3/8 Remaining work =1-3/8=5/8 75 mens 1 days work = 75/720=5/48Now 5/48 work is done by them in 1 day. 5/8 work is done by them in 48 x 5/ 5 x 8 = 6 days.
Related Solutions
45 men can complete a work in 16 days. Four days after they started working, 36 more men joined them. How many days will they now take to complete the remaining work?
View Solution45 men can complete a work in 16 days. Six days after they started working, 30 more men joined them. How many days will they now take to complete the remaining work?
View Solution12 men complete a work in 18 days. Six days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work ?
View SolutionThree men can complete a plece of work in 6 days. Two days after they started the work, 3 more men joined them. How many days will they take to complete the remaining work?
View Solution14 men can complete a work in 12 days. 4 days after they started the work, 2 more men joined them. How many days will they take to complete the remaining work ?
View Solution12 men can complete a work within 9 days. After 3 days they started the work, 6 men joined them to replace 2 men. How many days will they take to complete the remaining work?
View SolutionTwelve men can complete a work in 8 days. Three days after they started the work, 3 more men joined them. In how many days will all of them together complete the remaining work ?
View Solution12 men can do a piece of work in 90 days. After 30 days from the start of the work 2 men left the work and 8 men joined. In how many days will it take to complete the remaining work?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View Solution18 men can complete a work in 9 days. After they have worked for 5 days, 6 more men join them. How many days will they take to complete the remaining work ?
18 पुरुष किसी कार्य को 9 दिनों में पूरा कर सकते हैं | उनके 5 दिनों तक कार्य कर लेने के बाद, 6 अतिरिक्त पुरुष उनके साथ हो गए | शेष कार्य करने में उन्हें कितना समय लगेगा ?
View Solution16 women take 12 days to complete a work which can be completed by 12 men in 8 days. 16 men started working and after 3 days 10 men left 4 women joined them. How many days will they take to complete the remaining work?
View SolutionSix men can complete a work in 12 days. Two days later, 6 more men joined them. How many days will they take to complete the remaining work?
View Solution8 men can complete a work in 40 days. If 2 more men join them, how many days will it take to complete the same work?
View SolutionA piec of work can be done by 12 men in 24 days. They started the work and after 4 days then 6 more men joined them. How many days will they all take to complete the remaining work ?
View Solution14 persons can complete a work in 16 days. 8 persons started the work 12 days after they started the work 8 more persons joined them. How many days will they take to complete the remaining work ?
View Solution18 men can do a piece of work in 9 days. After working for 5 days 6 more men join them. In how many days will they take to complete the remaining work?
View SolutionA work which 12 men can complete in 8 days can be completed by 16 women in 12 days. 16 men started working and after 3 days 10 men left and 4 women joined. In how many days will it take to complete the remaining work?
View SolutionThree men can complete a work in 6 days. Two days after they started their work, 3 more persons joined them. Accordingly, in how many days will they complete the remaining work?
View Solution12 आदमी किसी कार्य को 90 दिनों में कर सकते है कार्य छोड़ प्रारभ होने के 30 दिनों के बाद 2 आदमियों ने कार्य को पूरा करने में कितने दिन लगेंगे ?
View Solution24 men can complete a piece of work in 15 days. 2 days after
the 24 men started working, 4 men left the work. How
many more days will the remaining men now take to
complete the remaining work?
View Solution