Question

A man and a boy can complete a piece of work together in 24 days. If for the last boy alone does the work then it is completed in 28 days. How long the man will take to complete the work alone ? a 72 days b 24 days c 20 days d 36 days

Text Solution
Verified by Experts

Correct option d 36 days Explanation: According to question 1 M + 1B complete the work in 24 days. Last 6 days boy alone does work. They worked together for 22 days Because the whole work complete in 28 days. Assume total work = 24 units. 1M+1Bper day work = 1 unit 1M+1B do the work in 22 days = 22 units work Rest work = 24-22 units = 2 units Rest work done by Boy in 6 days Hence Per day work of boy = 2/6 = 1/3 unit per dayMan per day work = 1 -1/3 = 2/3Man alone can do the work in =


Related Solutions