Question

A and B can together finish a work in 30 days. They worked together for 20 days and then B left and A finished the remaining work in 20 days so A can finished whole work in : a 50 days b 60 days c 48 days d 54 days

Text Solution
Verified by Experts

Correct option b 60 daysExplanation: According to question A+B complete work in 30 days Take L.C.M. ofA+B’s time to calculate the total work Assume total work 30 unitsHence A+B work/day = 1 unit/day A+B’s 20 days work = 20×1 unit/day = 20 units Rest work = 30 – 20 – 10 units Now  Rest work done by A in 20 daysThen one day’s work of A = 10/20 = 1/2Total work done by A in =Total units of work = A+B × 30 = 2×30 = 60 A’s efficiency = 1Total time = 60/1 = 60 days


Related Solutions