A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days he found that he had already done 2/3 of the work. How many men can be discharged now so that the work may finish in time? a 48 b 56 c 40 d 50
Correct option b 56 Explanation:Let ‘n’ no of men he discharged
Related Solutions
A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done of the work. How many men can be discharge now so that the work may finish in time?
View SolutionA contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done of the work.
How many men can be discharged now so that the work may finish in time?
View SolutionA contractor undertook to finish a work in 92 days and employed 110 men. After 48 days, he found that he had already done part of the work, the number of men he can withdraw so that the work may still be finished in time is :
View SolutionA contractor took a contract to finish a work in 80 days. He employed 300 men and after 60 days he had to employ 100 more men and then the work was finished 2 days earlier. By how many days would the work be finished if 100 extra men were not employed?
View Solution36 workmen are employed to finish a certain work in 48 days. But it is found that in 24 days only 2/5 work is done. How many more men must be employed to finish the work in time?
View Solution56 men can finish a work in 24 days. In how many days can 42 men finish the same work?
View Solution120 men working 10 hours a day can finish a piece of work in 85 days. After 10 days all the men went on strike and the work was stopped for 25 days. In order to finish the work on time, additional men should be employed so that they can finish the work on time by working 8 hours a day?
View SolutionA contractor took a contract to complete a work in 40 days. He initially employed 100 men and after 35 days, he employed 100 more and completed the work on time. If that extra person had not employed then after how many days would the work have been finished after the right time?
View Solution140 men were employed to finish a piece of work in 80 days. After 50 days 10 more men were employed. After how many days will the work be finished now?
View SolutionIf 40 men can finish a piece of work in 60 days. In how many days will 75 , men finish the same work ?
View SolutionA contractor employs 36 men on a job and they do 1/2 of the work in 16 days. He employs 12 additional men to complete the remainder of the work. In how many days will the remaining work be finished?
View Solution60 men can finish a work in 50 days. If 20 men join the work every 10 days, then in how many days will the work be finished?
View Solution40 men complete one-third of a work in 40 days. How many more men should be employed to finish the rest of the work in 50 more days ?
View SolutionA man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?
View Solution3 पुरुष किसी काम को 6 दिनों में समाप्त कर सकते है उनके काम शुरू करने के 2 दिनों के वे कितने दिनों में समाप्त करेंगे ?
View SolutionIf 40 men can finish a piece of work in 26 days, how many men will be required to finish it in 20 days?
View Solution40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View Solution40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?
View Solution