A work-force of 420 men with a contractor can finish a certain piece of work in 9 months. How many extra men must he employ to complete the job in 7 months?
As the number of workers is inversely proportional to time taken:
420×9=x×7
⇒x=420×97
⇒x=540
∴ Extra men needed:540−420=120
Related Playlists
Similar Questions
A work force of 50 men with a contractor can finish a piece of work in 5 months. In how many months the same work can be completed by 125 men?
View SolutionIf 28 men working 8 hours per day can finish a piece of work in 10 days. How many hours per day 40 men must work to complete the same work in 8 days.
View SolutionAn employer has a workforce of 300 employees to finish a project in 8 months.How many extra employees should he employ to complete the project in 6 months?
View Solution8 men can finish a piece of work in 15 hours.In how many hours can 20 men finish it?
View Solution7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work in 8 days ?
View Solution45 men can complete a piece of work in 12 days. In how many days will 36 men be able to complete it?
View SolutionIf 36 men can finish a piece of work in 35 days.how many days will 15 men take to do it ?
View SolutionA contractor undertook a contract to complete a part of a stadium in 9 months with a team of 560 persons. Later on, it was required to complete the job in 5 months. How many extra persons should he employ to complete the work?
View Solution7 men can complete a piece of work in 12 days. How many additional men will be required to complete double the work
View Solution15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?
View Solution