Doubtnut Promotions Sticky

A job can be completed by 6 men and 8 women in 10 days. 26 men and 48 women can finish the same work in 2 days. 15 men and 20 women can do the same work in - days.

A

4 days

B

6 days

C

2 days

D

8 days

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we need to establish the work rates of men and women based on the information given in the question.

Step 1: Determine the total work done by 6 men and 8 women in 10 days.

Let the work done by 1 man in 1 day be M and the work done by 1 woman in 1 day be W.

From the first condition:
- 6 men and 8 women can complete the work in 10 days.

The total work W can be expressed as:
W=(6M+8W)×10

Step 2: Determine the total work done by 26 men and 48 women in 2 days.

From the second condition:
- 26 men and 48 women can complete the work in 2 days.

The total work W can also be expressed as:
W=(26M+48W)×2

Step 3: Set the two expressions for total work equal to each other.

From Step 1 and Step 2, we have:
(6M+8W)×10=(26M+48W)×2

Step 4: Simplify the equation.

Expanding both sides:
60M+80W=52M+96W

Rearranging gives:
60M52M=96W80W
8M=16W

Step 5: Find the ratio of men to women.

Dividing both sides by 8:
M=2W

This means the ratio of men to women is:
MW=21

Step 6: Use the ratio to find the work done by 15 men and 20 women.

Now we need to find out how many days it will take for 15 men and 20 women to complete the work.

Using the ratio M=2W:
- Work done by 15 men in one day is 15M=15×2W=30W.
- Work done by 20 women in one day is 20W.

Thus, the total work done by 15 men and 20 women in one day is:
30W+20W=50W

Step 7: Calculate the total work W.

From the first condition, we can find W:
W=(6M+8W)×10
Substituting M=2W:
W=(6×2W+8W)×10
W=(12W+8W)×10=20W×10=200W

Step 8: Calculate the number of days for 15 men and 20 women to complete the work.

Now, we can find the number of days D it takes for 15 men and 20 women to complete the work:
D=Total WorkWork per day=200W50W=4 days

Final Answer:
The number of days it will take for 15 men and 20 women to complete the work is 4 days.

---

|
Updated on:7/8/2024

Topper's Solved these Questions


Similar Questions


Knowledge Check

  • Question 1 - Select One

    If 5 men or 9 women can do a piece of work in 19 days. 3 men and 6 women will do the same work in how many days ?

    A10 days
    B12 days
    C13 days
    D15 days
  • Question 2 - Select One

    If 5 men or 9 women can do a piece of work in 19 days. 3 men and 6 women will do the same work in how many days ?

    A10 days
    B12 days
    C13 days
    D15 days
  • Question 3 - Select One

    In how manu days can the work be done by 9 men and 15 women ?
    (i) 6 men and 5 women can complete the cork in 6 days.
    (ii) 3 men and 4 women can complete the work in 10 days
    (iii) 18 men and 15 women can complete the work in 2 days.

    A(iii) only
    BAll (i), (ii) and (iii)
    CAny two
    DAny one