Doubtnut Promotions Sticky

12 men can complete a work in 30 days by working 9 hours a day. What is the number of men required to complete 10 times of this work in 24 days by working 5 hours a day ?

Video Solution
Doubtnut Promotions Banner
Text Solution
Verified by Experts

The correct Answer is:270 men

|
Answer

Step by step video, text & image solution for 12 men can complete a work in 30 days by working 9 hours a day. What is the number of men required to complete 10 times of this work in 24 days by working 5 hours a day ? by Maths experts to help you in doubts & scoring excellent marks in Class 8 exams.

Updated on:21/07/2023

Related Playlists


Knowledge Check

  • Question 1 - Select One

    If 20 men complete a work in 56 days by working 10 hours a day how many days will 40 men take to complete the same work by working 8 hours a day?

    A30
    B25
    C48
    D35
  • Question 1 - Select One

    If 15 men can complete a work in 16 days by working 8 hours daily, then in how many days will 10 men complete the work by working 12 hours daily?

    Aa) 15
    Bb) 12
    Cc) 10
    Dd) 16
  • Question 1 - Select One

    18 men can do 3 units of work in 10 days by doing 8 hours in a day. Then find the required number of days taken by 10 men to complete 5 units of work if they work 6 hours in a day

    A32 days
    B45 days
    C36 days
    D40 days
  • Question 1 - Select One

    24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :

    A32 men
    B30 men
    C35 men
    D36 men
  • Question 1 - Select One

    If 20 men take 15 days to complete a certain amount of work working at 10 hours per day, then how many more men are required to complete twice the previous work in 10 days working at 12 hours a day?

    A10
    B20
    C30
    D40
  • Question 1 - Select One

    12 men and 18 boys working 712 hours a day can do a work in 60 days. If one man works equal to 2 boys, then the number of boys required to help 21 men to do twice the work in 50 days working 9 hours a day will be:

    A42
    B44
    C46
    DNone of these
  • Question 1 - Select One

    18 persons working 8 hours a day can complete 3 units of works in 10 days. How many persons are required to complete 5 units of that work in 16 days working 6 hours a day?

    A25
    B15
    C20
    D9

Similar Questions