Ashok takes twice as much time as Arun and thrice as much time as Alok together finish the work in one day. Ashok can finish the work in
4 days
2 days
6 days
3 days
The correct Answer is:C
To solve the problem, we need to determine how long Ashok takes to finish the work alone, given that he takes twice as much time as Arun and thrice as much time as Alok, and that together they finish the work in one day.
1. Define Variables:
- Let the time taken by Arun to complete the work be x days.
- Then, the time taken by Ashok will be 2x days (since Ashok takes twice as much time as Arun).
- Let the time taken by Alok be y days.
- According to the problem, Ashok takes thrice as much time as Alok, so 2x=3y.
2. Express Alok's Time in Terms of Arun's Time:
- From 2x=3y, we can express y in terms of x:
y=2x3
3. Calculate the Work Done:
- The work done by each person in one day can be expressed as:
- Arun's work rate: 1x
- Ashok's work rate: 12x
- Alok's work rate: 1y=32x (substituting y from above)
4. Total Work Rate:
- The total work rate of Ashok, Arun, and Alok together is:
Total Work Rate=1x+12x+32x
- Simplifying this:
Total Work Rate=1+12+32x=1+22x=32x
5. Set Total Work Rate to Complete Work in One Day:
- Since they complete the work in one day, we set the total work rate equal to 1:
32x=1
6. Solve for x:
- Rearranging gives:
3=2x⟹x=32
7. Calculate Ashok's Time:
- Since Ashok takes 2x days:
Ashok's time=2×32=3 days
Final Answer:
Ashok can finish the work in 3 days.
---
- Let the time taken by Arun to complete the work be x days.
- Then, the time taken by Ashok will be 2x days (since Ashok takes twice as much time as Arun).
- Let the time taken by Alok be y days.
- According to the problem, Ashok takes thrice as much time as Alok, so 2x=3y.
- From 2x=3y, we can express y in terms of x:
y=2x3
- The work done by each person in one day can be expressed as:
- Arun's work rate: 1x
- Ashok's work rate: 12x
- Alok's work rate: 1y=32x (substituting y from above)
- The total work rate of Ashok, Arun, and Alok together is:
Total Work Rate=1x+12x+32x
- Simplifying this:
Total Work Rate=1+12+32x=1+22x=32x
- Since they complete the work in one day, we set the total work rate equal to 1:
32x=1
- Rearranging gives:
3=2x⟹x=32
- Since Ashok takes 2x days:
Ashok's time=2×32=3 days
Ashok can finish the work in 3 days.
Similar Questions
A takes twice as much time as B and C take thrice as much time as B to finish a work. Working together, they can finish the work in 12 days. Find the number of days needed for A to do the work alone.
View SolutionA takes twice as much time as B or thrice as much time as C to finish a piece of work. Working together, they can finish the work in 2 days. B can do the work alone in : a. 4 days b. 6 days c. 8 days d. 12 days
View Solution
Knowledge Check
A takes twice as much time as B and thrice as much time as C finish a piece of work. Working together, they can finish the work in 2 days. A can do the work alone in:
A4 daysB6 daysC8 daysD12 daysA is twice as good a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work?
A11 daysB21 daysC28 daysD30 daysA is twice as efficient as B and B is thrice as efficient as C. Working together, they can finish a certain work in 5 days. If A and C worked together for 5 days then B alone would complete the remaining work in .......
A8 daysB5 daysC6 daysD4 days
Rahul takes twice as such time as Manick and thrice as much time a Sachin a job. If working together, they can complete the job in 4 days, find the time taken by each of them separately to complete the work.
View SolutionA works twice as much as B in the same time period. Together, they finish the work in 14 days. In how many days can it be done by each separately?
View SolutionA does half as much work as B, and C does half as much work as A and B together. If C alone can finish the work in 40 days, then all together will finish the work in (B) 15 days (A) 13(13) days (D) 30 days (C) 20 days
View SolutionA is twice as fast a workman as B and together they finish a piece of work in 14 days. In how many days can A alone finish the work ?
View SolutionA is twice as good a workman as B and together they finish a piece of work in 7 days. In how many days can A alone finish the work?
View Solution