Rahul takes twice as such time as Manick and thrice as much time a Sachin a job. If working together, they can complete the job in 4 days, find the time taken by each of them separately to complete the work.

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

To solve the problem, we need to find the time taken by Rahul, Manik, and Sachin to complete a job individually, given that they can complete the job together in 4 days.

1. Define Variables:
- Let the time taken by Manik to complete the job be M days.
- Since Rahul takes twice as much time as Manik, the time taken by Rahul will be R=2M days.
- Since Rahul takes thrice as much time as Sachin, we can express Sachin's time as S=R3=2M3 days.

2. Calculate Work Done:
- The work done by each person in one day can be expressed as:
- Work done by Manik in one day = 1M
- Work done by Rahul in one day = 1R=12M
- Work done by Sachin in one day = 1S=32M

3. Combine Their Work:
- When working together, their combined work done in one day is:
Total work done in one day=1M+12M+32M
- Simplifying this:
=1M+12M+32M=1+1+32M=52M

4. Set Up the Equation:
- Since they can complete the job in 4 days when working together, the total work done in one day is:
52M=14

5. Solve for M:
- Cross-multiplying gives:
54=2M20=2MM=10

6. Find the Time Taken by Each:
- Now that we have M:
- Time taken by Manik M=10 days.
- Time taken by Rahul R=2M=2×10=20 days.
- Time taken by Sachin S=2M3=2×103=2036.67 days.

Final Answer:
- Manik takes 10 days.
- Rahul takes 20 days.
- Sachin takes approximately 6.67 days.

Updated on:7/8/2024
|


Topper's Solved these Questions


Similar Questions


Knowledge Check

  • A takes twice as much time as B and thrice as much time as C finish a piece of work. Working together, they can finish the work in 2 days. A can do the work alone in:

    A4 days
    B6 days
    C8 days
    D12 days
  • If 40 workers can complete a task in 24 days, then, find the time taken by 16 workers to complete twice the work.

    A125 days
    B122 days
    C120 days
    D116 days
  • A can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.

    A8 days
    B10 days
    C6 days
    D9 days