Rahul takes twice as such time as Manick and thrice as much time a Sachin a job. If working together, they can complete the job in 4 days, find the time taken by each of them separately to complete the work.
To solve the problem, we need to find the time taken by Rahul, Manik, and Sachin to complete a job individually, given that they can complete the job together in 4 days.
1. Define Variables:
- Let the time taken by Manik to complete the job be M days.
- Since Rahul takes twice as much time as Manik, the time taken by Rahul will be R=2M days.
- Since Rahul takes thrice as much time as Sachin, we can express Sachin's time as S=R3=2M3 days.
2. Calculate Work Done:
- The work done by each person in one day can be expressed as:
- Work done by Manik in one day = 1M
- Work done by Rahul in one day = 1R=12M
- Work done by Sachin in one day = 1S=32M
3. Combine Their Work:
- When working together, their combined work done in one day is:
Total work done in one day=1M+12M+32M
- Simplifying this:
=1M+12M+32M=1+1+32M=52M
4. Set Up the Equation:
- Since they can complete the job in 4 days when working together, the total work done in one day is:
52M=14
5. Solve for M:
- Cross-multiplying gives:
5⋅4=2M⟹20=2M⟹M=10
6. Find the Time Taken by Each:
- Now that we have M:
- Time taken by Manik M=10 days.
- Time taken by Rahul R=2M=2×10=20 days.
- Time taken by Sachin S=2M3=2×103=203≈6.67 days.
Final Answer:
- Manik takes 10 days.
- Rahul takes 20 days.
- Sachin takes approximately 6.67 days.
- Let the time taken by Manik to complete the job be M days.
- Since Rahul takes twice as much time as Manik, the time taken by Rahul will be R=2M days.
- Since Rahul takes thrice as much time as Sachin, we can express Sachin's time as S=R3=2M3 days.
- The work done by each person in one day can be expressed as:
- Work done by Manik in one day = 1M
- Work done by Rahul in one day = 1R=12M
- Work done by Sachin in one day = 1S=32M
- When working together, their combined work done in one day is:
Total work done in one day=1M+12M+32M
- Simplifying this:
=1M+12M+32M=1+1+32M=52M
- Since they can complete the job in 4 days when working together, the total work done in one day is:
52M=14
- Cross-multiplying gives:
5⋅4=2M⟹20=2M⟹M=10
- Now that we have M:
- Time taken by Manik M=10 days.
- Time taken by Rahul R=2M=2×10=20 days.
- Time taken by Sachin S=2M3=2×103=203≈6.67 days.
- Manik takes 10 days.
- Rahul takes 20 days.
- Sachin takes approximately 6.67 days.
Topper's Solved these Questions
Similar Questions
A takes twice as much time as B and C take thrice as much time as B to finish a work. Working together, they can finish the work in 12 days. Find the number of days needed for A to do the work alone.
View SolutionRahul is twice efficient as Ram. If both of them can complete the work in 12 days. Then find the number of days Rahul would take to complete the work above.
View Solution
Knowledge Check
A takes twice as much time as B and thrice as much time as C finish a piece of work. Working together, they can finish the work in 2 days. A can do the work alone in:
A4 daysB6 daysC8 daysD12 daysIf 40 workers can complete a task in 24 days, then, find the time taken by 16 workers to complete twice the work.
A125 daysB122 daysC120 daysD116 daysA can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.
A8 daysB10 daysC6 daysD9 days
A can do a job in 12 days and B can do the same job in 6 days, in how many days working together they can complete the job?
View SolutionX can complete a job in 12 days. If X and Y work together, they can complete the job in 6(23) days. 'Y' alone can complete the job on
View SolutionA can complete a work in 12 days and B complete the same work in 15 days. Find the time taken by them when A and B worked together.
View SolutionA takes twice the time taken by B and thrice the time taken by C to do a particular piece of work. Working together, they can complete the work in 2 days. Find the number of days taken by A, B and C respectively to complete the work alone
View SolutionX can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in
View Solution