Working 8 hours a day, 120, persons can dig a canal 162 m long 12 m wide and 2 m deep in 8days . Working 6 hours a day, the number of persons that will be required to dig a canal 729 m long, 10 m wide and 3 m deep in 32 days is
250
175
200
225
The correct Answer is:D
To solve the problem, we will follow these steps:
Step 1: Calculate the volume of the first canal
The volume of a canal can be calculated using the formula:
Volume=Length×Width×Depth
For the first canal:
- Length = 162 m
- Width = 12 m
- Depth = 2 m
So, the volume is:
Volume=162×12×2
Step 2: Calculate the total work done in person-hours for the first canal
The total work done can be calculated as:
Total Work=Number of Persons×Hours per Day×Days
For the first canal:
- Number of Persons = 120
- Hours per Day = 8
- Days = 8
So, the total work done is:
Total Work=120×8×8
Step 3: Calculate the work done per cubic meter for the first canal
Now, we can find the work done per cubic meter by dividing the total work by the volume calculated in Step 1.
Step 4: Calculate the volume of the second canal
Using the same volume formula for the second canal:
- Length = 729 m
- Width = 10 m
- Depth = 3 m
So, the volume is:
Volume=729×10×3
Step 5: Calculate the total work required for the second canal
Using the work done per cubic meter from Step 3, we can find the total work required for the second canal by multiplying the volume calculated in Step 4 by the work done per cubic meter.
Step 6: Calculate the number of persons required for the second canal
Using the total work required for the second canal and the working hours per day, we can find the number of persons required:
Number of Persons=Total Work RequiredHours per Day×Days
For the second canal:
- Hours per Day = 6
- Days = 32
Final Calculation
Now we can substitute all the values and calculate the number of persons required.
The volume of a canal can be calculated using the formula:
Volume=Length×Width×Depth
- Length = 162 m
- Width = 12 m
- Depth = 2 m
Volume=162×12×2
The total work done can be calculated as:
Total Work=Number of Persons×Hours per Day×Days
- Number of Persons = 120
- Hours per Day = 8
- Days = 8
Total Work=120×8×8
Now, we can find the work done per cubic meter by dividing the total work by the volume calculated in Step 1.
Using the same volume formula for the second canal:
- Length = 729 m
- Width = 10 m
- Depth = 3 m
Volume=729×10×3
Using the work done per cubic meter from Step 3, we can find the total work required for the second canal by multiplying the volume calculated in Step 4 by the work done per cubic meter.
Using the total work required for the second canal and the working hours per day, we can find the number of persons required:
Number of Persons=Total Work RequiredHours per Day×Days
- Hours per Day = 6
- Days = 32
Now we can substitute all the values and calculate the number of persons required.
Similar Questions
12 men working 8 hours per day complete a piece of work in 10 days. To complete the same work in 8 days, working 15 hours a day, the number of men required is a. 4 b. 5 c. 6 d. 8
View SolutionIf 25 men can do a piece of work in 36 days working 10 hours a day, then how many men are required to complete the work working 6 hours a day in 20 days?
View Solution
Knowledge Check
8 workers can build a wall 18 m long, 2 m broad and 12 m high in 10 days, working 9 hours a day. Find how many workers will be able to build a wall 32 m long, 3 m broad and 9 m high in 8 days working 6 hours a day?
A16B20C30D108 workers can build a wall 18 m long, 2 m broad and 12 m high in 10 days, working 9 hours a day. Find how many workers will be able to build a wall 32 m long, 3 m broad and 9 m high in 8 days working 6 hours a day?
A16B20C30D10Working 7 hours in a day, 4 men can do a piece of work in 8 days. Working 8 hours in a day, the required number of men to perform the same work in 4 days will be
A1. 8B2. 4C3. 7D4. 9
12 men can complete a work in 30 days by working 9 hours a day. What is the number of men required to complete 10 times of this work in 24 days by working 5 hours a day ?
View SolutionA certain number of person can dig a trench 100 m long , 50 m broad and 10 m deep in 10 days. The same number of persons can dig another trench 20 m broad and 15 m deep in 30 days. The length of the second trench is 400 m b. 800 m c. 500 m d. 900 m
View Solution40 men can build a wall 200 m long in 12 days, working 8 h a day. What will be the number of days that 30 men will take to build a similar wall 300 m long, working 6 h per day
View Solution24 men working 8 hours a day can finish a work in 10 days. Working at the rate of 10 hours a day, the number of men required to finish the same work in 6 days is:
View Solution10 men working 8 hours day can do a work in 30 days. In how many days will 12 men working 4 hours a day take do the same work?
View Solution