X is 60% more efficient than Y. and Y alone can do a work in 80 days. Working together, X and Y will complete 52% of the same work in:

A

16 days

B

15 days

C

18 days

D

20 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem step by step, we can follow these steps:

Step 1: Determine the efficiency of Y
Y can complete the work in 80 days. Therefore, the efficiency of Y (E_Y) can be calculated as:
EY=180 (work per day)

Step 2: Calculate the efficiency of X
Since X is 60% more efficient than Y, we can express the efficiency of X (E_X) as:
EX=EY+0.6×EY=1.6×EY
Substituting the value of E_Y:
EX=1.6×180=1.680=150 (work per day)

Step 3: Calculate the combined efficiency of X and Y
The combined efficiency (E_XY) of X and Y working together is:
EXY=EX+EY=150+180
To add these fractions, we need a common denominator. The least common multiple of 50 and 80 is 400:
EXY=8400+5400=13400 (work per day)

Step 4: Calculate the total work
The total work can be calculated based on Y's efficiency:
Total Work=EY×Time taken by Y=180×80=1 (whole work)

Step 5: Calculate the amount of work to be completed
We need to find out how long it will take for X and Y to complete 52% of the work:
Work to be completed=0.52×1=0.52 (of the whole work)

Step 6: Calculate the time taken to complete 52% of the work
Using the combined efficiency, we can find the time (T) taken to complete 52% of the work:
T=Work to be completedCombined Efficiency=0.5213400=0.52×40013
Calculating this gives:
T=2081316 days

Final Answer
Thus, X and Y together will complete 52% of the work in approximately 16 days.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A is 20% more efficient than B. If B alone can complete a piece of work in 12 days, then A alone can complete the same work in how many days?

    A10
    B12
    C14
    D15
  • A is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?

    A10
    B12
    C14
    D16
  • P is 20% more efficient than Q. If Q alone can finish a work in 10 days, then in how many days will P alone finish the work?

    A813
    B8.5
    C9
    D12