X is 60% more efficient than Y. and Y alone can do a work in 80 days. Working together, X and Y will complete 52% of the same work in:
16 days
15 days
18 days
20 days
The correct Answer is:A
To solve the problem step by step, we can follow these steps:
Step 1: Determine the efficiency of Y
Y can complete the work in 80 days. Therefore, the efficiency of Y (E_Y) can be calculated as:
EY=180 (work per day)
Step 2: Calculate the efficiency of X
Since X is 60% more efficient than Y, we can express the efficiency of X (E_X) as:
EX=EY+0.6×EY=1.6×EY
Substituting the value of E_Y:
EX=1.6×180=1.680=150 (work per day)
Step 3: Calculate the combined efficiency of X and Y
The combined efficiency (E_XY) of X and Y working together is:
EXY=EX+EY=150+180
To add these fractions, we need a common denominator. The least common multiple of 50 and 80 is 400:
EXY=8400+5400=13400 (work per day)
Step 4: Calculate the total work
The total work can be calculated based on Y's efficiency:
Total Work=EY×Time taken by Y=180×80=1 (whole work)
Step 5: Calculate the amount of work to be completed
We need to find out how long it will take for X and Y to complete 52% of the work:
Work to be completed=0.52×1=0.52 (of the whole work)
Step 6: Calculate the time taken to complete 52% of the work
Using the combined efficiency, we can find the time (T) taken to complete 52% of the work:
T=Work to be completedCombined Efficiency=0.5213400=0.52×40013
Calculating this gives:
T=20813≈16 days
Final Answer
Thus, X and Y together will complete 52% of the work in approximately 16 days.
---
Y can complete the work in 80 days. Therefore, the efficiency of Y (E_Y) can be calculated as:
EY=180 (work per day)
Since X is 60% more efficient than Y, we can express the efficiency of X (E_X) as:
EX=EY+0.6×EY=1.6×EY
Substituting the value of E_Y:
EX=1.6×180=1.680=150 (work per day)
The combined efficiency (E_XY) of X and Y working together is:
EXY=EX+EY=150+180
To add these fractions, we need a common denominator. The least common multiple of 50 and 80 is 400:
EXY=8400+5400=13400 (work per day)
The total work can be calculated based on Y's efficiency:
Total Work=EY×Time taken by Y=180×80=1 (whole work)
We need to find out how long it will take for X and Y to complete 52% of the work:
Work to be completed=0.52×1=0.52 (of the whole work)
Using the combined efficiency, we can find the time (T) taken to complete 52% of the work:
T=Work to be completedCombined Efficiency=0.5213400=0.52×40013
Calculating this gives:
T=20813≈16 days
Thus, X and Y together will complete 52% of the work in approximately 16 days.
Similar Questions
Anand is 50% more efficient than Bharath and Bharath is 100% more efficient that Chandu. Working together, they can complete a work in 10 days. In how many days can Anand alone do the work?
View SolutionA is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?
View Solution
Knowledge Check
A is 20% more efficient than B. If B alone can complete a piece of work in 12 days, then A alone can complete the same work in how many days?
A10B12C14D15A is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?
A10B12C14D16P is 20% more efficient than Q. If Q alone can finish a work in 10 days, then in how many days will P alone finish the work?
A813B8.5C9D12
A can do a work in 15 days. B is 25% more effcient than a In how many days working together A and B is complete the same work ?
View SolutionTo complete a certain task, X is 40% more efficient than Y, and Z is 40% less efficient than Y. Working together, they can complete the task in 21 days. Y and Z together worked for 35 days. The remaining work will be completed by X alone in:
किसी निश्चित कार्य को पूरा करने के लिए, X, Y की तुलना में 40% अधिक कार्य कुशल है तथा Z, Y से 40% कम कार्य कुशल है| एक साथ कार्य करते हुए, वे इस कार्य को 21 दिनों में पूरा कर सकते हैं | Y तथा Z ने 35 दिनों तक एक साथ कार्य किया | शेष कार्य A अकेला कितने दिनों में पूरा करेगा ?
View SolutionX alone can do a piece of work in 12 days and Y alone can do the same work in 6 days. In how many days will both together complete the same work?
View SolutionB is 20% more efficient than A. B started the work & do it for
x days. And then B is replaced by A, A completed the
remaining work in x+8 days. Ratio of work done by A & B is
3:2 IN how many days A & B working together complete
the whole work?
View SolutionA is 40% more efficient than B and C is 20% less efficient than B. Working together, they can finish a work is 5 days. In how many days will A alone complete 70% of that work?
View Solution