A' can complete a work in 15 days and 'B' can complete the same work in 20 days. Working together, in how many days will they complete 70% of the same work ?
7
6
5
8
The correct Answer is:B
To solve the problem, we need to determine how many days A and B will take to complete 70% of the work when working together.
1. Determine the work done by A and B in one day:
- A can complete the work in 15 days. Therefore, A's work rate (efficiency) is:
Efficiency of A=115 (work per day)
- B can complete the work in 20 days. Therefore, B's work rate (efficiency) is:
Efficiency of B=120 (work per day)
2. Calculate the combined work rate of A and B:
- When A and B work together, their combined efficiency is:
Combined Efficiency=Efficiency of A+Efficiency of B=115+120
- To add these fractions, we need a common denominator. The least common multiple of 15 and 20 is 60. Thus:
115=460and120=360
- Therefore:
Combined Efficiency=460+360=760
3. Determine the total work to be completed:
- We need to find out how much work corresponds to 70% of the total work. Since the total work is considered as 1 (100%), 70% of the work is:
Work to be completed=0.7 (or 70100=710)
4. Calculate the time taken to complete 70% of the work:
- Using the formula:
Time=WorkEfficiency
- We substitute the work to be completed and the combined efficiency:
Time=0.7760=0.7×607=427=6 days
Final Answer:
A and B, working together, will complete 70% of the work in 6 days.
- A can complete the work in 15 days. Therefore, A's work rate (efficiency) is:
Efficiency of A=115 (work per day)
- B can complete the work in 20 days. Therefore, B's work rate (efficiency) is:
Efficiency of B=120 (work per day)
- When A and B work together, their combined efficiency is:
Combined Efficiency=Efficiency of A+Efficiency of B=115+120
- To add these fractions, we need a common denominator. The least common multiple of 15 and 20 is 60. Thus:
115=460and120=360
- Therefore:
Combined Efficiency=460+360=760
- We need to find out how much work corresponds to 70% of the total work. Since the total work is considered as 1 (100%), 70% of the work is:
Work to be completed=0.7 (or 70100=710)
- Using the formula:
Time=WorkEfficiency
- We substitute the work to be completed and the combined efficiency:
Time=0.7760=0.7×607=427=6 days
A and B, working together, will complete 70% of the work in 6 days.
Similar Questions
If A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
View SolutionA alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both 4 and B together can complete half of the total work?
View Solution
Knowledge Check
A man completes a work in 12 days another man completes the same work 10 days. If both work together, then how many days will the work completed ?
A5B5511C1/11D11A and B together can complete a work in 35 days while A alone can complete the same work in 60 days. In how many days, B alone will be able to complete the same work?
A80 daysB84 daysC84 daysD92 daysA can complete a piece of work in 20 days and B can complete 20% of the work in 6 days. If they work together in how many days can they finish 50% of the work, if they work together?
A12B6C8D9
A alone can complete a work in 12 days and B alone can complete the same work in 24 days. In how many days can A and B together complete the same work?
View SolutionVijay and Sahil together complete a piece of work in 40 days, Sahil and Ranjit can complete the same work in 48 days and Ranjit and Vijay can complete the same work in 60 days. In how many days can all the three complete the same work while working together?
View Solution24 boys can complete a work in 12 days while 16 men can complete the same work in 9 days. In how many days will 12 boys and 12 men together complete the same work ?
View SolutionA can complete a work in 12 days and B can complete the same work in 24 days. Find the time taken by both A and B together to complete the work.
View SolutionA can complete a work in 20 days and B can complete the same work in 25 days . If both of them work together, in 3 days what per cant of the total work will be completed ?
View Solution