'A' can complete the 60% of the work in 9 days, while 'B' can complete the work in 7 1 2 days. If they work together, then in how many days will the work be completed?

A

7

B

6

C

5

D

0.04

Video Solution
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem, we need to determine how much work 'A' and 'B' can complete together in a day and then find out how many days it will take them to finish the entire work.

1. Calculate the total work done by 'A':
- 'A' completes 60% of the work in 9 days.
- Therefore, the total work (let's denote it as W) can be calculated as:
0.6W=Work done by A in 9 days
W=0.6W0.6=90.6=15 days (for 100% work)

2. Calculate the work rate of 'A':
- If 'A' completes the entire work in 15 days, then the work rate of 'A' is:
Rate of A=115 (work per day)

3. Calculate the work rate of 'B':
- 'B' can complete the work in 712 days, which is equal to 7.5 days.
- Therefore, the work rate of 'B' is:
Rate of B=17.5=215 (work per day)

4. Calculate the combined work rate of 'A' and 'B':
- When 'A' and 'B' work together, their combined work rate is:
Combined Rate=Rate of A+Rate of B=115+215=315=15 (work per day)

5. Calculate the total time taken to complete the work together:
- If they complete 15 of the work in one day, then the total time taken to complete the entire work (1 unit of work) is:
Time=1 (total work)15 (work per day)=5 days

Final Answer:
Thus, 'A' and 'B' together will complete the work in 5 days.

|


Similar Questions


Knowledge Check

  • A can complete a piece of work in 20 days and B can complete 20% of the work in 6 days. If they work together in how many days can they finish 50% of the work, if they work together?

    A12
    B6
    C8
    D9
  • A can complete a piece of work in 6 days while B can complete the same work in 12 days. If they work together and complete it then, the portion of the work done by A is

    A14
    B12
    C23
    D13
  • A and B together can complete a work in 12 days. A alone can complete it in 20 days. If B does the work only for half a day daily, then in how many days A and B together will complete the work? 110 days b. 11 days c. 15 days d. 20 days

    A10 days
    B11 days
    C15 days
    D20 days