'A' can complete the 60% of the work in 9 days, while 'B' can complete the work in days. If they work together, then in how many days will the work be completed?
7
6
5
0.04
The correct Answer is:C
To solve the problem, we need to determine how much work 'A' and 'B' can complete together in a day and then find out how many days it will take them to finish the entire work.
1. Calculate the total work done by 'A':
- 'A' completes 60% of the work in 9 days.
- Therefore, the total work (let's denote it as W) can be calculated as:
0.6W=Work done by A in 9 days
W=0.6W0.6=90.6=15 days (for 100% work)
2. Calculate the work rate of 'A':
- If 'A' completes the entire work in 15 days, then the work rate of 'A' is:
Rate of A=115 (work per day)
3. Calculate the work rate of 'B':
- 'B' can complete the work in 712 days, which is equal to 7.5 days.
- Therefore, the work rate of 'B' is:
Rate of B=17.5=215 (work per day)
4. Calculate the combined work rate of 'A' and 'B':
- When 'A' and 'B' work together, their combined work rate is:
Combined Rate=Rate of A+Rate of B=115+215=315=15 (work per day)
5. Calculate the total time taken to complete the work together:
- If they complete 15 of the work in one day, then the total time taken to complete the entire work (1 unit of work) is:
Time=1 (total work)15 (work per day)=5 days
Final Answer:
Thus, 'A' and 'B' together will complete the work in 5 days.
- 'A' completes 60% of the work in 9 days.
- Therefore, the total work (let's denote it as W) can be calculated as:
0.6W=Work done by A in 9 days
W=0.6W0.6=90.6=15 days (for 100% work)
- If 'A' completes the entire work in 15 days, then the work rate of 'A' is:
Rate of A=115 (work per day)
- 'B' can complete the work in 712 days, which is equal to 7.5 days.
- Therefore, the work rate of 'B' is:
Rate of B=17.5=215 (work per day)
- When 'A' and 'B' work together, their combined work rate is:
Combined Rate=Rate of A+Rate of B=115+215=315=15 (work per day)
- If they complete 15 of the work in one day, then the total time taken to complete the entire work (1 unit of work) is:
Time=1 (total work)15 (work per day)=5 days
Thus, 'A' and 'B' together will complete the work in 5 days.
Similar Questions
A and B working together can complete the work in 12 days. A can complete the work in 20 days. If B does work for half day each day, then in what time can the work be completed.
View SolutionThe ratio of work efficiency of A & B is 2:5 . If A can complete a work in 10 days. In how many days the work can be completed by B and when they work together , in how many days the work would be completed ?
View Solution
Knowledge Check
A can complete a piece of work in 20 days and B can complete 20% of the work in 6 days. If they work together in how many days can they finish 50% of the work, if they work together?
A12B6C8D9A can complete a piece of work in 6 days while B can complete the same work in 12 days. If they work together and complete it then, the portion of the work done by A is
A14B12C23D13A and B together can complete a work in 12 days. A alone can complete it in 20 days. If B does the work only for half a day daily, then in how many days A and B together will complete the work? 110 days b. 11 days c. 15 days d. 20 days
A10 daysB11 daysC15 daysD20 days
A can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?
View SolutionA can complete one-third of a work in 5 days and B can complete 40% of the work in 10 days. In how many days both A and B together can complete the work?
View SolutionA can do a work in x days while B can do the same work in y days then in how many days will they complete the work, working together?
View SolutionA and B separately can complete a work in 6 days and 3 days respectively. If they work together. Then in how many days will they complete the work ?
View SolutionA can complete a work in 25 days, B can complete the same work in 20 days. If they work together for 10 days and remaining work is completed by C alone in 10 days. In how many days A, B, and C together can complete the same task?
View Solution