X can do half and Y can do one-third of a certain work in 5 and 10 days, respectively. Working together. in how many days will they be able to complete double of the work?

A

1612

B

712

C

15

D

16

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem step by step, we will first determine the work done by X and Y individually, then calculate their combined efficiency, and finally find out how long it will take them to complete double the work together.

Step 1: Determine the work done by X and Y

- X can do half of the work in 5 days.
Therefore, the total work (W) can be calculated as:
Total Work=2×Work done by X=2×12=1 (whole work)
Thus, X can complete the whole work in:
Time taken by X=5 days×2=10 days

- Y can do one-third of the work in 10 days.
Therefore, the total work can be calculated as:
Total Work=3×Work done by Y=3×13=1 (whole work)
Thus, Y can complete the whole work in:
Time taken by Y=10 days×3=30 days

Step 2: Calculate the efficiency of X and Y

- Efficiency of X:
Efficiency of X=1 (whole work)10 days=110 work/day

- Efficiency of Y:
Efficiency of Y=1 (whole work)30 days=130 work/day

Step 3: Calculate the combined efficiency of X and Y

- Combined Efficiency:
Combined Efficiency=Efficiency of X+Efficiency of Y=110+130
To add these fractions, we need a common denominator:
LCM of 10 and 30=30
Thus,
110=330and130=130
Therefore,
Combined Efficiency=330+130=430=215 work/day

Step 4: Calculate the time taken to complete double the work

- Double the work:
Since the total work is 1, double the work is:
Double Work=2 (whole work)

- Time taken to complete double the work:
Time=Total WorkCombined Efficiency=2215=2×152=15 days

Final Answer:
Thus, X and Y together will take 15 days to complete double the work.

---

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • A can do a work in 36 days and B in 12 days. If they work to gether in how many days will they be able to do the work?

    A8
    B6
    C10
    D9
  • If A alone can do a work in 12 days and B alone can do it in 8 days, Working together, in how many days will they complete it?

    A445 days
    B4 days
    C345 days
    D6 days
  • A, B and c can complete a piece of work in 10, 20 and 60 days respectively. Working together can complete the same work in how many days?

    A5
    B6
    C10
    D8