X can do half and Y can do one-third of a certain work in 5 and 10 days, respectively. Working together. in how many days will they be able to complete double of the work?
1612
712
15
16
The correct Answer is:C
To solve the problem step by step, we will first determine the work done by X and Y individually, then calculate their combined efficiency, and finally find out how long it will take them to complete double the work together.
Step 1: Determine the work done by X and Y
- X can do half of the work in 5 days.
Therefore, the total work (W) can be calculated as:
Total Work=2×Work done by X=2×12=1 (whole work)
Thus, X can complete the whole work in:
Time taken by X=5 days×2=10 days
- Y can do one-third of the work in 10 days.
Therefore, the total work can be calculated as:
Total Work=3×Work done by Y=3×13=1 (whole work)
Thus, Y can complete the whole work in:
Time taken by Y=10 days×3=30 days
Step 2: Calculate the efficiency of X and Y
- Efficiency of X:
Efficiency of X=1 (whole work)10 days=110 work/day
- Efficiency of Y:
Efficiency of Y=1 (whole work)30 days=130 work/day
Step 3: Calculate the combined efficiency of X and Y
- Combined Efficiency:
Combined Efficiency=Efficiency of X+Efficiency of Y=110+130
To add these fractions, we need a common denominator:
LCM of 10 and 30=30
Thus,
110=330and130=130
Therefore,
Combined Efficiency=330+130=430=215 work/day
Step 4: Calculate the time taken to complete double the work
- Double the work:
Since the total work is 1, double the work is:
Double Work=2 (whole work)
- Time taken to complete double the work:
Time=Total WorkCombined Efficiency=2215=2×152=15 days
Final Answer:
Thus, X and Y together will take 15 days to complete double the work.
---
Therefore, the total work (W) can be calculated as:
Total Work=2×Work done by X=2×12=1 (whole work)
Thus, X can complete the whole work in:
Time taken by X=5 days×2=10 days
Therefore, the total work can be calculated as:
Total Work=3×Work done by Y=3×13=1 (whole work)
Thus, Y can complete the whole work in:
Time taken by Y=10 days×3=30 days
Efficiency of X=1 (whole work)10 days=110 work/day
Efficiency of Y=1 (whole work)30 days=130 work/day
Combined Efficiency=Efficiency of X+Efficiency of Y=110+130
To add these fractions, we need a common denominator:
LCM of 10 and 30=30
Thus,
110=330and130=130
Therefore,
Combined Efficiency=330+130=430=215 work/day
Since the total work is 1, double the work is:
Double Work=2 (whole work)
Time=Total WorkCombined Efficiency=2215=2×152=15 days
Thus, X and Y together will take 15 days to complete double the work.
Similar Questions
Knowledge Check
A can do a work in 36 days and B in 12 days. If they work to gether in how many days will they be able to do the work?
A8B6C10D9If A alone can do a work in 12 days and B alone can do it in 8 days, Working together, in how many days will they complete it?
A445 daysB4 daysC345 daysD6 daysA, B and c can complete a piece of work in 10, 20 and 60 days respectively. Working together can complete the same work in how many days?
A5B6C10D8
If A can do a piece of work in 4 days, B can do the same work in 8 days and C can do the same work in 12 days , then working together , how many days will they take to complete the work ?
View SolutionA and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?
View SolutionA and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?
View SolutionA and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?
View SolutionA and B can complete a piece of work in 15 days and 10 days, respectively . They work together for 4 days and then B leavs. In how many days will A alone complete the remaining work ?
View Solution