Two workers A and B are engaged to do a piece of work . A working alone would take 14 hours more to complete the work than when A and B work together B working alone would take 3 1 2 hours more than when A and B work together . The time required to finish the work together is

A

7 hours

B

5 hours

C

6 hours

D

8 hours

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:A


To solve the problem, let's denote the time taken by A and B to complete the work together as x hours.

1. Express the time taken by A and B:
- If A works alone, he takes x+14 hours.
- If B works alone, he takes x+3.5 hours.

2. Set up the work equations:
- The work done by A in one hour is 1x+14.
- The work done by B in one hour is 1x+3.5.
- The work done by A and B together in one hour is 1x.

3. Combine the work equations:
1x+14+1x+3.5=1x

4. Clear the fractions by multiplying through by x(x+14)(x+3.5):
x(x+3.5)+x(x+14)=(x+14)(x+3.5)

5. Expand and simplify:
- Left side: x2+3.5x+x2+14x=2x2+17.5x
- Right side: x2+3.5x+14x+49=x2+17.5x+49

So we have:
2x2+17.5x=x2+17.5x+49

6. Rearranging the equation:
2x2x2+17.5x17.5x49=0
x249=0

7. Solve for x:
x2=49x=7 (since time cannot be negative)

Thus, the time required to finish the work together is 7 hours.

Updated on:8/8/2024
|


Similar Questions


Knowledge Check

  • Two workers A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work that when work together. If B worked alone, would take 412 hours more than when work together. The time required to finish the work together is

    A5 hours
    B4 hours
    C8 hours
    D6 hours
  • Two workers A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work that when work together. If B worked alone, would take 412 hours more than when work together. The time required to finish the work together is

    A1. 5 hours
    B2. 8 hours
    C3. 4 hours
    D4. 6 hours
  • Two workers A and B are engaged to do a piece of work. Working alone, A takes 8 hours more to complete the work than if both worked together. On the other hand, working alone, B would need 412 hours more to complete the work than if both worked together. How much time would they take to complete the job working together?

    A4Hours
    B5Hours
    C6 Hours
    D7 Hours