Two workers A and B are engaged to do a piece of work . A working alone would take 14 hours more to complete the work than when A and B work together B working alone would take hours more than when A and B work together . The time required to finish the work together is
7 hours
5 hours
6 hours
8 hours
The correct Answer is:A
To solve the problem, let's denote the time taken by A and B to complete the work together as x hours.
1. Express the time taken by A and B:
- If A works alone, he takes x+14 hours.
- If B works alone, he takes x+3.5 hours.
2. Set up the work equations:
- The work done by A in one hour is 1x+14.
- The work done by B in one hour is 1x+3.5.
- The work done by A and B together in one hour is 1x.
3. Combine the work equations:
1x+14+1x+3.5=1x
4. Clear the fractions by multiplying through by x(x+14)(x+3.5):
x(x+3.5)+x(x+14)=(x+14)(x+3.5)
5. Expand and simplify:
- Left side: x2+3.5x+x2+14x=2x2+17.5x
- Right side: x2+3.5x+14x+49=x2+17.5x+49
So we have:
2x2+17.5x=x2+17.5x+49
6. Rearranging the equation:
2x2−x2+17.5x−17.5x−49=0
x2−49=0
7. Solve for x:
x2=49⟹x=7 (since time cannot be negative)
Thus, the time required to finish the work together is 7 hours.
- If A works alone, he takes x+14 hours.
- If B works alone, he takes x+3.5 hours.
- The work done by A in one hour is 1x+14.
- The work done by B in one hour is 1x+3.5.
- The work done by A and B together in one hour is 1x.
1x+14+1x+3.5=1x
x(x+3.5)+x(x+14)=(x+14)(x+3.5)
- Left side: x2+3.5x+x2+14x=2x2+17.5x
- Right side: x2+3.5x+14x+49=x2+17.5x+49
2x2+17.5x=x2+17.5x+49
2x2−x2+17.5x−17.5x−49=0
x2−49=0
x2=49⟹x=7 (since time cannot be negative)
Similar Questions
Two workers A and B are engaged to do a piece of work.Working alone, A takes 8 hours more to complete the workthan if both worked together. On the other hand, workingalone, B would need 412 hours more to complete the work than if both worked together. How much time would they take tocomplete the job working together?
View SolutionA takes 4 hours more than that of A and B working together to finish certain piece of work. While B takes 9 hours more than that of A and B working together. Then find in how many hours A and B working together can finish the work?
View Solution
Knowledge Check
Two workers A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work that when work together. If B worked alone, would take 412 hours more than when work together. The time required to finish the work together is
A5 hoursB4 hoursC8 hoursD6 hoursTwo workers A and B are engaged to do a piece of work. A working alone would take 8 hours more to complete the work that when work together. If B worked alone, would take 412 hours more than when work together. The time required to finish the work together is
A1. 5 hoursB2. 8 hoursC3. 4 hoursD4. 6 hoursTwo workers A and B are engaged to do a piece of work. Working alone, A takes 8 hours more to complete the work than if both worked together. On the other hand, working alone, B would need 412 hours more to complete the work than if both worked together. How much time would they take to complete the job working together?
A4HoursB5HoursC6 HoursD7 Hours
When A alone does a piece of work , he takes 16 days more than the time taken by (A+B) to complete the work, while B alone takes 9 days more than the time taken by (A + B) to finish the work. What time,AandBtogether will take to finish this work?
View SolutionA alone takes 4 more days to complete a work, in that time A and B can complete it together and B alone takes 16 more days to complete the same. In how many days they will do it together?
View SolutionIf A had worked alone he would have taken 63 hours to do the task. What is B's share, if A and B work together on a task finishing it in 36 hours and they get paid Rs 5,950 for it?
View SolutionA can do a picec of work in 10 days and B is 25% more
efficient than A. In what time will the work be finished if A
and B work together ?
View SolutionA and B together can do a piece of work in 9 days. If A does thrice the work of B in a given time, the time A alone will take to finish the work is
View Solution