A,B and C can do a piece of work in 10,15 and 30 days, respectively. If B and C both assist A on every third day, then in how many days can the work be completed?

A

812

B

5

C

8

D

712

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:C


To solve the problem, we need to determine how much work A, B, and C can complete together, given their individual work rates, and how the work progresses over the days according to the conditions provided.

Step 1: Determine the work rates of A, B, and C.
- A can complete the work in 10 days, so A's work rate is 110 of the work per day.
- B can complete the work in 15 days, so B's work rate is 115 of the work per day.
- C can complete the work in 30 days, so C's work rate is 130 of the work per day.

Step 2: Calculate the combined work rate of A, B, and C.
On the days when B and C assist A (every third day), we need to calculate their combined work rate:
- Combined work rate of A, B, and C on the third day:
Work rate=110+115+130
To add these fractions, we need a common denominator. The least common multiple of 10, 15, and 30 is 30.
110=330,115=230,130=130
So,
Combined work rate=330+230+130=630=15

Step 3: Calculate the work done in a 3-day cycle.
- On the first two days, only A works:
Work done by A in 2 days=2×110=210=15
- On the third day, A, B, and C work together:
Work done on the third day=15
- Total work done in 3 days:
Total work in 3 days=15+15=25

Step 4: Determine how many cycles are needed to complete the work.
To complete the entire work (1 unit of work), we need to find out how many 3-day cycles are required:
- In each cycle of 3 days, 25 of the work is completed.
- Let n be the number of cycles needed:
n×25=1n=52=2.5
This means we need 2 complete cycles (6 days) and a part of another cycle.

Step 5: Calculate the remaining work after 2 cycles.
- Work done in 2 cycles (6 days):
2×25=45
- Remaining work:
145=15

Step 6: Calculate how much time is needed to complete the remaining work.
- On the 7th day, A works alone:
Work done by A on 7th day=110
- On the 8th day, A works alone again:
Work done by A on 8th day=110
- On the 9th day, A, B, and C work together:
Work done on 9th day=15

After the 8th day, A has done 15 of the work, and on the 9th day, they complete the remaining 15 of the work.

Total Days Taken
- Total days = 6 days (2 cycles) + 2 days (7th and 8th) + 1 day (9th) = 9 days.

Thus, the total time taken to complete the work is 9 days.

|


Similar Questions


Knowledge Check

  • If A, B, and C can do a piece of work in 15, 30, and 60 days respectively. In how many days together they will do the same work?

    A10 days
    B12 days
    C60/11 days
    D60/7 days
  • A, B and c can complete a piece of work in 10, 20 and 60 days respectively. Working together can complete the same work in how many days?

    A5
    B6
    C10
    D8
  • A and B working separately can do a piece of work in 10 days and 15 days respectively. If they work on alternate days beginning with A, in how many days will the work be complete?

    A18 days
    B13 days
    C12 days
    D6 days