A,B and C can do a piece of work in 10,15 and 30 days, respectively. If B and C both assist A on every third day, then in how many days can the work be completed?
812
5
8
712
The correct Answer is:C
To solve the problem, we need to determine how much work A, B, and C can complete together, given their individual work rates, and how the work progresses over the days according to the conditions provided.
Step 1: Determine the work rates of A, B, and C.
- A can complete the work in 10 days, so A's work rate is 110 of the work per day.
- B can complete the work in 15 days, so B's work rate is 115 of the work per day.
- C can complete the work in 30 days, so C's work rate is 130 of the work per day.
Step 2: Calculate the combined work rate of A, B, and C.
On the days when B and C assist A (every third day), we need to calculate their combined work rate:
- Combined work rate of A, B, and C on the third day:
Work rate=110+115+130
To add these fractions, we need a common denominator. The least common multiple of 10, 15, and 30 is 30.
110=330,115=230,130=130
So,
Combined work rate=330+230+130=630=15
Step 3: Calculate the work done in a 3-day cycle.
- On the first two days, only A works:
Work done by A in 2 days=2×110=210=15
- On the third day, A, B, and C work together:
Work done on the third day=15
- Total work done in 3 days:
Total work in 3 days=15+15=25
Step 4: Determine how many cycles are needed to complete the work.
To complete the entire work (1 unit of work), we need to find out how many 3-day cycles are required:
- In each cycle of 3 days, 25 of the work is completed.
- Let n be the number of cycles needed:
n×25=1⟹n=52=2.5
This means we need 2 complete cycles (6 days) and a part of another cycle.
Step 5: Calculate the remaining work after 2 cycles.
- Work done in 2 cycles (6 days):
2×25=45
- Remaining work:
1−45=15
Step 6: Calculate how much time is needed to complete the remaining work.
- On the 7th day, A works alone:
Work done by A on 7th day=110
- On the 8th day, A works alone again:
Work done by A on 8th day=110
- On the 9th day, A, B, and C work together:
Work done on 9th day=15
After the 8th day, A has done 15 of the work, and on the 9th day, they complete the remaining 15 of the work.
Total Days Taken
- Total days = 6 days (2 cycles) + 2 days (7th and 8th) + 1 day (9th) = 9 days.
Thus, the total time taken to complete the work is 9 days.
- A can complete the work in 10 days, so A's work rate is 110 of the work per day.
- B can complete the work in 15 days, so B's work rate is 115 of the work per day.
- C can complete the work in 30 days, so C's work rate is 130 of the work per day.
On the days when B and C assist A (every third day), we need to calculate their combined work rate:
- Combined work rate of A, B, and C on the third day:
Work rate=110+115+130
To add these fractions, we need a common denominator. The least common multiple of 10, 15, and 30 is 30.
110=330,115=230,130=130
So,
Combined work rate=330+230+130=630=15
- On the first two days, only A works:
Work done by A in 2 days=2×110=210=15
- On the third day, A, B, and C work together:
Work done on the third day=15
- Total work done in 3 days:
Total work in 3 days=15+15=25
To complete the entire work (1 unit of work), we need to find out how many 3-day cycles are required:
- In each cycle of 3 days, 25 of the work is completed.
- Let n be the number of cycles needed:
n×25=1⟹n=52=2.5
This means we need 2 complete cycles (6 days) and a part of another cycle.
- Work done in 2 cycles (6 days):
2×25=45
- Remaining work:
1−45=15
- On the 7th day, A works alone:
Work done by A on 7th day=110
- On the 8th day, A works alone again:
Work done by A on 8th day=110
- On the 9th day, A, B, and C work together:
Work done on 9th day=15
- Total days = 6 days (2 cycles) + 2 days (7th and 8th) + 1 day (9th) = 9 days.
Similar Questions
A and B working separately can do a piece of work in 10 days and 15 days respectively. If they work on alternate days beginning with A, in how many days will the work be complete?
View SolutionA, B and C can do a piece of work in 12, 15 and 20 days respectively. In how many days will all three do this work together ?
View Solution
Knowledge Check
If A, B, and C can do a piece of work in 15, 30, and 60 days respectively. In how many days together they will do the same work?
A10 daysB12 daysC60/11 daysD60/7 daysA, B and c can complete a piece of work in 10, 20 and 60 days respectively. Working together can complete the same work in how many days?
A5B6C10D8A and B working separately can do a piece of work in 10 days and 15 days respectively. If they work on alternate days beginning with A, in how many days will the work be complete?
A18 daysB13 daysC12 daysD6 days
A and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?
View SolutionA and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?
View SolutionA and B can do a work in 30 days and 10 days respectively. If they work on alternate days beginning with A, in how many days will the work be completed?
View SolutionA, B and C can complete a piece of work in 10, 20 and 60 days respectively. Working together they can complete the same work in how many days?
View SolutionA and B working separately can do a piece of work in 9 and 12 days respectively. If they work for a day alternately, A beginning, in how many days, he work will be completed?
View Solution