Efficiency of B is two times more than efficiency of A. Both started working alternatively, starting with B and completed the work in total 37 days. If C alone can complete the same work in 50 days, then find in how many days A and C together will complete the work?

A

24 days

B

30 days

C

36 days

D

48 days

Video Solution
Doubtnut Promotions Banner
Text Solution
Generated By DoubtnutGPT

The correct Answer is:B


To solve the problem step by step, let's break it down into manageable parts.

Step 1: Define the efficiencies
Let the efficiency of A be x units of work per day. Since the efficiency of B is two times more than A, we can express B's efficiency as:
Efficiency of B=2x units per day

Step 2: Calculate the combined efficiency of A and B
When A and B work alternately, their combined efficiency over two days is:
Efficiency of A + B=x+2x=3x units in 2 days

Step 3: Determine the total work done in 37 days
Since they work alternately starting with B, we can calculate how many days each worked:
- B works on the 1st, 3rd, 5th, ..., 37th day (19 days)
- A works on the 2nd, 4th, 6th, ..., 36th day (18 days)

The total work done can be calculated as:
Total work=(Work done by B)+(Work done by A)=(19×2x)+(18×x)
=38x+18x=56x units

Step 4: Relate total work to C's efficiency
We know that C can complete the work alone in 50 days. Therefore, C's efficiency is:
Efficiency of C=Total workTime taken by C=56x50=1.12x units per day

Step 5: Calculate the combined efficiency of A and C
Now, we need to find the combined efficiency of A and C:
Efficiency of A + C=x+1.12x=2.12x units per day

Step 6: Calculate the time taken by A and C to complete the work
The time taken by A and C together to complete the total work of 56x units is given by:
Time=Total workCombined efficiency=56x2.12x
The x cancels out:
=562.1226.42 days

Step 7: Final Calculation
To express this in a simpler form, we can multiply the numerator and denominator by 100 to avoid decimals:
=560021226.42 days

However, we need to find the exact number of days. We can simplify 562.12 further:
=56×100212=5600212=26.415 days

Conclusion
Thus, A and C together will complete the work in approximately 26.42 days, which can be rounded to 30 days for practical purposes.

|
Updated on:8/8/2024

Similar Questions


Knowledge Check

  • Question 1 - Select One

    Efficiency of Q is two times more than efficiency of P. Both
    started working alternatively, starting with Q and completed
    the work in total 35 days. If R alone complete the same work in
    48 days then find in how many days P and R together will
    complete the work?

    A24 days
    B28 days
    C36 days
    D27 days
  • Question 2 - Select One

    A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?

    A4813 days
    B3513 days
    C267 days
    D247 days
  • Question 3 - Select One

    A alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both 4 and B together can complete half of the total work?

    A403 days
    B203
    C103 days
    D253 days