A alone can complete a task in 10 days A,B worked together for 3 days after which C replaced B. A was 50% more efficient than C, After A and C had worked for three days, 13% task was incomplete. In approximately how many days B (working alone) can complete the entire work?
24
64
12
43
The correct Answer is:D
To solve the problem step by step, we will break down the information given and calculate the required values.
Step 1: Determine A's efficiency
A can complete the task in 10 days. Therefore, A's work done in one day is:
Work done by A in 1 day=110
Step 2: Determine C's efficiency
It is given that A is 50% more efficient than C. If we denote C's efficiency as x, then:
A=1.5×C⟹110=1.5x⟹x=115
Thus, C can complete the task in 15 days.
Step 3: Determine B's efficiency
Let B's efficiency be y. Since we do not know B's efficiency yet, we will keep it as 1y.
Step 4: Calculate the work done by A and B together in 3 days
In 3 days, the work done by A and B together is:
Work done by A in 3 days=3×110=310
The work done by B in 3 days is:
Work done by B in 3 days=3×1y=3y
Thus, the total work done by A and B together in 3 days is:
Total work in 3 days=310+3y
Step 5: Calculate the work done by A and C together in the next 3 days
After 3 days, C replaces B, and A and C work together for another 3 days. The work done by A and C in 3 days is:
Work done by A in 3 days=3×110=310
Work done by C in 3 days=3×115=15
Thus, the total work done by A and C together in 3 days is:
Total work in 3 days=310+15=310+210=510=12
Step 6: Calculate total work done and remaining work
The total work done by A and B in the first 3 days and A and C in the next 3 days is:
Total work done=(310+3y)+12
We know that 13% of the task is incomplete, meaning 87% of the task is complete. Therefore:
(310+3y)+12=87100
Step 7: Solve for B's efficiency
Convert all fractions to a common denominator:
310=30100,12=50100
Thus, we have:
30100+3y+50100=87100
This simplifies to:
80100+3y=87100
Subtracting 80100 from both sides gives:
3y=7100
Cross-multiplying gives:
3×100=7y⟹300=7y⟹y=3007≈42.86
Step 8: Conclusion
Thus, B can complete the entire work alone in approximately 43 days.
A can complete the task in 10 days. Therefore, A's work done in one day is:
Work done by A in 1 day=110
It is given that A is 50% more efficient than C. If we denote C's efficiency as x, then:
A=1.5×C⟹110=1.5x⟹x=115
Thus, C can complete the task in 15 days.
Let B's efficiency be y. Since we do not know B's efficiency yet, we will keep it as 1y.
In 3 days, the work done by A and B together is:
Work done by A in 3 days=3×110=310
The work done by B in 3 days is:
Work done by B in 3 days=3×1y=3y
Thus, the total work done by A and B together in 3 days is:
Total work in 3 days=310+3y
After 3 days, C replaces B, and A and C work together for another 3 days. The work done by A and C in 3 days is:
Work done by A in 3 days=3×110=310
Work done by C in 3 days=3×115=15
Thus, the total work done by A and C together in 3 days is:
Total work in 3 days=310+15=310+210=510=12
The total work done by A and B in the first 3 days and A and C in the next 3 days is:
Total work done=(310+3y)+12
We know that 13% of the task is incomplete, meaning 87% of the task is complete. Therefore:
(310+3y)+12=87100
Convert all fractions to a common denominator:
310=30100,12=50100
Thus, we have:
30100+3y+50100=87100
This simplifies to:
80100+3y=87100
Subtracting 80100 from both sides gives:
3y=7100
Cross-multiplying gives:
3×100=7y⟹300=7y⟹y=3007≈42.86
Thus, B can complete the entire work alone in approximately 43 days.
Similar Questions
Knowledge Check
A is 50% more efficient than B and C is 40% less efficient than B. Working together, they can complete a task in 10 days. In how many days, will A alone complete 150% of that task?
A, B से अधिक कार्य कुशल है और C, B से 40% कम कार्य कुशल है | एक साथ कार्य करते हुए वे किसी कार्य को दस दिनों में पूरा कर सकते हैं | इस कार्य का 150% भाग पूरा करने में A को अकेले कितने दिन लगेंगे ?A33B35C28D31A is 50% more efficient than B and C is 40% less efficient than B. Working together, they can complete a task in 20 days. In how many days will C alone complete 30% of that task?
A, B से 50% अधिक कार्य कुशल है तथा C, B से 40% कम कार्य कुशल है | एक साथ कार्य करते हुए, वे किसी कार्य को 20 दिनों में पूरा कर सकते हैं | C अकेले इस कार्य का 30% भाग कितने दिनों में पूरा करेगा ?A31B33C35D29A and B complete a work in 6 days. A alone can complete the work in 10 days. In how many days can B alone complete the work ?
A4B15C154D16
A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?
View SolutionA is 20% more efficient than B. If B alone can complete a piece of work in 12 days, then A alone can complete the same work in how many days?
View SolutionA is 20% more efficient than B.B can do a piece of work in 20 days. In how many days can A do the same work?
View SolutionA is 40% more efficient than B and C is 20% less efficient than B. Working together, they can finish a task in 15 days. In how many days, will B alone will complete 75% of the task?
A, B से 40% अधिक कार्य कुशल है तथा C, B से 20% कम कार्य कुशल है | एक साथ कार्य करते हुए, वे किसी कार्य को 15 दिनों में समाप्त कर सकते हैं |B अकेले इस कार्य का 75% भाग कितने दिनों में पूरा करेगा ?
View SolutionA and B can together complete a task 40 days. They worked together for 30 days and then left. A finished the remaining task in next 22 days. In how many days A alone can finish the task?
View Solution